REPUBLIKA SLOVENIJA MINISTRSTVO ZA OlgILJE IN PROSTOR NATURA 2000 SITE MANAGEMENT PROGRAMME 2.007-2013 Operational programme CIP - Kataložni zapis o publikaciji Narodna in univerzitetna knjižnica, Ljubljana 502.5(497.4-751.3)"2007/2013" BIBIČ, Andrej Natura 2000 site management programme : 2007-2013 : operational programme / [text Andrej Bibič, Breda Ogorelec ; translated by Blaž Trebar, Zlatko Midžić ; photographs Matjaž Bedjanič ... [et al.] ; drawings Marjan Vaupotič, Jurij Mikuletič]. - Ljubljana : Ministry of the Environment and Spatial Planning, 2007 ISBN 978-961-6392-58-7 1. Gl. stv. nasl. 236944384 NATURA 2000 SITE MANAGEMENT PROGRAMME 2007-2013 Operational programme ^^Sřr * S FOREWORD Increasingly rapid rate of biodiversity loss, which is largely a consequence of human activities, has become a social concern to such an extent that over 150 countries of the world signed the Convention on Biodiversity in 1992. The vast majority of the Contracting States set as the target the reduction of current rate of biodiversity loss by 2010. A partial overview of achieving the target shall be done in the year when Slovenia is presiding the EU countries, at the ninth meeting of the Contracting States. The eyes of world public will be focused on Slovenia; therefore, our responsibility for the conservation of high level of Slovenian biodiversity shall be additionally examined. The EU Member States have set the establishment of the Natura 2000 network and its efficient management as one of the key objectives to stop the biodiversity loss. In Slovenia, 35,5 percent of the territory or 286 sites, respectively, important not only for conservation of species pursuant to the EU Directives, but also the endemic and nationally endangered ones have been included into the Natura 2000 network. Therefore, Slovenia contributes to the conservation of biodiversity in particular through the Natura 2000 network and the operational programme is an important contribution to a more targeted and efficient conservation. The adopted operational programme defines in details the protective objectives and measures in the Natura sites. Thereby, numerous stakeholders in these sites are given one of the key information for their work that contributes to quality of decision. The main objective of Natura 2000 is to preserve and increase biodiversity in the territory of the European Union for future generations by enabling a responsible sustainable development and a part of this objective is to stimulate traditional coexistence of people and nature. The Natura 2000 sites are living sites, to which also the people are giving the meaning, therefore, it is very important to seek developmental opportunities. The operational programme stresses some new opportunities for local or regional development, in particular in the field of agriculture, tourism, recreation and related activities. Conservation of high biodiversity in Slovenia shall contribute to the international reputation of the country during the Slovenian Presidency of the European Union, since the attention of global players of nature conservation shall be focused on Slovenia. In Slovenia, together with the Ministry of the Environment and Spatial Planning and the Ministry of Agriculture, Forestry and Food, the World Conservation Union (International Union for the Protection of Nature and Natural Resources, IUCN) has already signed the Declaration on cooperation in internationally recognised initiative for halting the rate of biodiversity loss Countdown 2010 - Save Our Planet. The core of the Slovenian commitments in this Declaration represents this specific operational programme. The adoption of the programme was a long and demanding process, in which many people have participated. On this occasion, I would like to thank all of you who contributed to the creation of this quality document through your activities - with a wish, that this activities and co-operation continue also in its implementation. Janez Podobnik Minister tu PREPARATION OF THE OPERATIONAL PROGRAMME - PROGRAMME OF THE MANAGEMENT OF NATURA 2000 SITES Slovenia is a country of the European Union with the largest part of the territory included in the Natura 2000 sites. Such a large portion of sites, which should be outstanding for their significance for the Natura species and habitat types according to the criteria of the Directive on Habitats and the Directive on Birds, means consequently that a large portion of this area is also outstanding for its qualities. Conservation of the existing qualities or concern that the existing state does not worsen in such a large part of the state territory is therefore a great challenge. However, providing the existing state is a very important contribution to achieving a favourable state of species and habitat types conservation. The Natura 2000 sites are also covered with sector legislation, which has frequently a long-lasting tradition in sustainable use of natural resources and established plans for their use. To avoid duplication of administrative structures for implementation of measures in the Natura 2000 sites, upon due consideration, the basic principle was to enter in these plans, in particular in the field of forests, hunting, fishery and later water management. So these plans are becoming important not only for the sustainable use of natural resources but also for conservation of the most endangered species and habitat types. The Rural Development Programme in particular is an instrument to encourage environmental functions of the agriculture. Measures from the operational programme therefore relate to the Rural Development Programme and complement Natura 2000. The Natura sites also partially comprise surfaces where the measures for nature protection are already being implemented (contractual protection and stewardship, temporary protection, protection by establishing protected area, restoration, identification in nature, restriction of viewing and visiting, restriction of practices that endanger the protected animal species) in order to achieve other objectives of nature protection, or they are to be implemented in the coming years (e.g. establishment of new protected areas). Here, the main principle was also to include protective objectives of Natura 2000 and actions for achieving them in the preparation and implementation of the actions. In accordance with the Bird Directive and the Habitat Directive, the detailed protective objectives are based on the existing knowledge of an individual species or a habitat type, especially of their ecologic requirements and actions to achieve these objectives are based on the existing legal framework. The first step was then to prepare proposals on the detailed protective objectives and actions to achieve them based on expert groundwork and other literature available and with knowledge of the legislative framework and the register of land use and some state aid. The results of the NCSA Project helped the Ministry to perform his step, further, the Institute Symbiosis, producer of the chapter on biodiversity was also of valuable assistance. In the further process of objectives formation, workshops within the framework of LIFE Project Natura 2000 in Slovenia - management models and information systems (holder the Institute of the Republic of Slovenia for Protection of Nature) were also helpful and included cooperation of public services (Slovenian Forest Service, Fisheries Research Institute of Slovenia, Agricultural Advisory Service of the Chamber of Agriculture and Forestry of Slovenia, Institute for Water of the Republic of Slovenia) in the preparation of the operational programme. Afterwards, phase of verification of ambitiousness of the objectives and feasibility of the actions with key stakeholders followed. Parallelly, due to the same time limits, inclusion of measures into the Rural Development Plan (holder the Ministry of Agriculture, Forestry and Food) and the programme of reinforcing regional developmental potentials (holders the Government Office for Local-Selfgovernment and Regional Policy and Ministry of the Economy) were taking place. The review of steps in preparation of the operational programme is provided in the timeline. Knowledge and data are a foundation of efficient actions and in the preparation of the operational programme, a considerable gap in the available knowledge between different taxon groups was found. Therefore, the objectives and measures for better-known taxon groups (e.g. bats, birds, forest habitat types) are more detailed and for the less known taxon groups only indicative. It has appeared thereby that the complexity of the field does not play any role, since even in the less complex fields defined only for some poorly known species only indicative objective have been set. An indispensable result of the programme preparation was therefore to review the most required expertise and data and fields of research development. However, monitoring will be the key to establish state of species and habitat types conservation. Consequently, the results of monitoring shall serve to assess success and, in the future, to formulate even better measures. A quarter of the Natura network is already designated as protected areas (parks, reserves, natural monuments), additional 10 percent are planned for designation until 2012. On these areas the provisions from the act on the protected area relevant as a measure to attain a protection objective are listed, or a starting point to be considered in drafting a protected area act or management plan. Implementation of measures and their contribution to sustainable development are strengthened by a range of investments and services tied to the development of park infrastructure for the advancement of tourist offers in the protected areas. On Natura sites which are not designated as protected areas a more general range of proposals has been developed together with interested local communities. Implementation of the operational programme measures also requires financial support. The key sources are the funds from the new financial perspective of the EU, together with the existing national funds. The new financial perspective earmarks much funds for Natura 2000, however they are diverse by the method of disbursement and partially dispersed. Thus, in the programme preparation domestic financial funds as well as the EU funds intended for Slovenia had to be collected, whereby cooperation with the key ministries was more constructive than ever before. Therefore, the funds in this perspective are significantly higher than ever before, however they might still be insufficient in view of the increasing demands and potential complications in disbursement in the coming years. Finally, I would like to thank all the individuals who contributed to this programme preparation and were over hundred. Besides all the co-workers from the Ministry of Environment and Spatial Planning the thanks for a significant contribution goes to the Symbiosis Institute or Jana Kus Veenvliet, respectively, to the Agricultural Advisory Service of the Chamber of Agriculture and Forestry of Slovenia, Slovenian Forest Service, Institute of the Republic of Slovenia for Protection of Nature, Sector of close-to-nature farming of the Ministry of Agriculture, Forestry and Food, Government Office for Local-Selfgovernment and Regional Policy and Ministry of the Economy, Centre for Cartography of Fauna and Flora, BirdLife Slovenia and to the authorities of the protected sites. Andrej Bibič http://www.rec-lj.si/projekti/NCSA/Dokumenti/NCSA_FR_SI_web.pdf http://www.zrsvn.si/life/sl/default.asp CONTENTS 1 INTRODUCTION.....................................................17 1.1 Legal framework for the Natura 2000 site management programme......18 1.1.1 Legal framework for preparation of the management programme...... 18 1.2 Purpose of the operational programme..................................24 2 CONTENT OF THE MANAGEMENT PROGRAMME.........27 2.1 Overview...............................................................28 2.1.1 Natura 2000 network contribution to biodiversity.................... 28 2.1.2 Natura 2000 network status ........................................ 29 2.1.3 Impact of activities on the attainment of objectives in the Natura 2000 network.............................................. 30 2.1.4 Quality of knowledge, data and information.......................... 31 2.2 Structure of the management programme...............................32 2.3 Detailed protection objectives...........................................34 2.4 Measures to attain protection objectives ................................35 2.4.1 Nature protection measures......................................... 36 2.4.1.1 Site protection and temporary site protection measures........ 37 2.4.2 Measures of modified use of natural resources........................ 42 2.4.2.1 Forestry .................................................... 43 2.4.2.2 Hunting .................................................... 44 2.4.2.3 Fishery ..................................................... 45 2.4.3 Measures of modified agricultural practice ........................... 45 2.4.4 Water management measures ....................................... 48 2.4.5 Other measures .................................................... 49 2.4.5.1 Measures of sustainable development aimed at direct benefits from Natura sites for the local population.................... 49 2.4.5.2 Monitoring ................................................. 51 2.4.5.3 Communications ............................................ 52 2.4.5.4 Education and training ...................................... 53 3 SUPPORT ACTIONS FOR EFFECTIVE MANAGEMENT OF THE NATURA SITES ............................................ 55 3.1 Cohesion of the European ecological network ...........................56 3.2 Indicators and monitoring of the above .................................56 3.3 Research and technology development..................................59 4 ANNEXES.............................................................61 4.1 References..............................................................62 4.1.1 General references.................................................. 62 4.1.2 Groundwork for measures........................................... 63 4.2 Detailed protection objectives and measures for their attainment on Natura sites..........................................................66 4.3 List of plans for the use of natural resources (i.e. plans which may prove directly necessary for the protection of Natura sites)..........72 4.3.1 Forest management plans........................................... 72 4.3.2 Hunting area plans and wild game management plans (LUO).......... 76 4.3.3 Fishery management plans of a fishery zone.......................... 80 4.4 Research activities in the basic and applied sciences that are indispensable to improving knowledge of the ecology of plant and animal species and habitat types....................................81 4.5 Monitoring indicators of the status of species and habitat types .........82 4.6 List of investments for the implementation of specific measures within the management of Natura and other protected areas, and development on the basis of opportunities created by these areas........90 4.7 Target research projects and studies aimed at defining objectives or measures .................................................102 NATURA 2000 IN SLOVENIA Slovenia's Nature and Biodiversity Slovenia is characterised by rich diversity in a rather small territory situated between the Alps, the Dinaric Mountains, the Pannonian plain and the Mediterranean. This variety is demonstrated in the geology of the area, its varied relief, climatic conditions, biodiversity, as well as landscape and cultural diversity. ^e review of habitats shows that all the basic categories are extremely rich: coastal and marine types, inland waters, scrub and grasslands, forests, bogs, fens and marshes, barren land (rocky habitats, screes, dunes, caves) as well as agricultural and urbanised landscapes. The principal characteristic of the landscapes is the intertwining of small units and its mosaic structure. Large areas of one habitat type are rare. Such composition is the result of the diversity of natural factors (i.e. the Mediterranean, Alpine or continental influence) and human activities (i.e. mowing, grazing). Forests, which cover 56 percent of the territory, are the prevailing habitat type. A substantial share is taken up by caves (7,400 registered caves), which is the result of the predominating carbonate bedrock that determines the appearance of the landscape and defines the composition of biodiversity. According to the available data, there are 22,000 registered plant and animal species in Slovenia. However, it is estimated that the actual number is between 50,000 and 120,000. ^e degree of endemism is considerably high in comparison to the smallness of the area1. 1 http://www.cbd.mop.gov.si/info/db/biological_landscape_diversity_in_slovenia.pdf Main characteristics Surface area 20,273 km2 Inhabitants 2.010.377 (2006) Geology juncture of four geotectonic units: Eastern Alps, Dinarids, Pannonian Basin, Adriatic- Apulian foothills (Placer, 2000), diverse rock structures Biogeographic regions the Alps (30 percent), the Dinaric Mountains (30 percent), the Mediterranean Basin (10 percent), and the Pannonian Plain (30 percent), covering a total area of 20,273 km2, give the country an ecotone character Relief varied relief, altitude above sea-level 0 to 2,864 metres 1/6 of the territory is of Quaternary sediments, some 44 percent carbonate bed-rock, mainly karstified areas (over 7,000 caves registered) Hydrological characteristics two drainage systems: 2/3 to the Black Sea, 1/3 to the Mediterranean Sea, five catchment areas: the Soča, Sava, Drava in Mura rivers, and the Slovenian Littoral relatively large karst area with no surface streams Vegetation cover 66 percent of the territory covered by forests and areas reverting to natural vegetation 28 percent of the territory is agricultural land Flora about 3,200 vascular plants 60 endemic taxa, including 22 narrow endemics with predominant distribution in Slovenia Fauna about 13,000 - 15,000 species (expected 50,000 up to 100,000) about 4,000 endemic taxa (above all cave animals)2 2 http://www.cbd.mop.gov.si/info/db/biological_landscape_diversity_in_slovenia .pdf, http://www.stat.si/doc/pub/slo_figures_07.pdf Basic facts on Natura 2000 in Slovenia In April 2004, Slovenia designated the Natura 2000 sites and undertook to suitably protect and manage them. ^ere are 286 Natura 2000 sites in total, encompassing approximately 36 percent of the country. With regard to the number of protected species and the proportion of its national territory included in the Natura 2000 network, Slovenia is at the very top of the European list, (terrestrial) rate being the highest in EU. A particular characteristic of Slovenia is its great diversity of animal and plant species in a small area, and its well-preserved nature. The sites are home to 111 threatened plant and animal species and 61 habitat types protected by the Habitats Directive as well as 105 species protected by the Wild Birds Directive. EU 25 spa, sci Habitat types 218 56 56 Birds 125 57 57 Mammals 51 16 Reptiles and amphibia 48 8 111 Fish 82 27 Invertebrates 134 33 Plants 572 27 Natura 2000 sites in Slovenia Special Protected Areas, designated under the Wild Birds Directive, in Slovenia: • number of sites: 26 • total area: 461.819 ha, which makes 23 percent of the national territory Sites of Community Interest in Slovenia: • number of sites: 260 • total area: 639.735 ha (32 percent of national territory) Two thirds of sites are forested, a substantial part consists of areas with little vegetation (mainly rock walls), 5 percent is areas above the tree line, and there are also notable areas of grasslands. 28 percent of the total Natura 2000 sites in Slovenia fall within existing protected areas (Triglav National Park, regional and landscape parks, reserves or nature monuments). 36 PERCENT OF NATIONAL TERRITORY 70 PERCENT ARE FORESTED 28 PERCENT WITHIN PROTECTED AREAS rj î í Pí INTRODUCTION 1.1 » LEGAL FRAMEWORK FOR THE NATURA 2000 SITE MANAGEMENT PROGRAMME 1.1.1 » LEGAL FRAMEWORK FOR PREPARATION OF THE MANAGEMENT PROGRAMME Law of the European Union The obligation to protect special protected areas, the Natura 2000 sites, derives from Council Directive 92/43/EEC of 21 May 1992 on the conservation of natural habitats and of wild fauna and flora (UL L No. 206 of 22 June 1992, p. 7, with amendments; hereinafter: Habitats Directive) in connection with Council Directive 79/409/EEC of 2 April 1979 on the conservation of wild birds (UL L No. 103 of 25 April 1979, p. 1, with amendments; hereinafter: Birds Directive). Paragraph 2 of Article 6 of the Habitats Directive imposes on the Member States, as of the date of their accession to the European Union, the responsibility to prevent deterioration of natural habitats and habitats of species, as well as the disturbance of species for which Natura 2000 sites have been designated, if such disturbance could significantly influence the objectives of this directive. ^is provision is valid for the proposed special protected areas that have been designated in accordance with the criteria and procedure from the Habitats Directive (paragraph 5 of Article 4) and for the areas designated in accordance with the Birds Directive (Article 7 of the Habitats Directive). The obligations resulting from the two directives have been transposed into the Slovenian legal order in their entirety, jointly with the regulations on nature conservation. EU bodies have also adopted the European Commission's communication entitled Halting the Loss of Biodiversity by 2010 - and Beyond (C0M[2006] 216 final), including the Council of the European Union, which adopted the mentioned report on 18 December 2006. In its decisions, the EU Council recommended to Member States to implement the action plan that forms part of the report. ^e operational programme at hand includes actions from the mentioned plan and provides the basis for its implementation in the Republic of Slovenia. Slovenian legal order ^e Environment Protection Act (Official Gazette of the Republic of Slovenia, No. 39/06 - official consolidated version, 49/06 - ZmetD, 66/06 - judicial decision of the Constitutional Court of the Republic of Slovenia, and 33/07 - ZPNačrt; hereinafter: ZVO-1) provides a systematic framework for nature conservation, of which biodiversity conservation is a fundamental part. ZVO-1 thus regulates the protection of the environment from overburdening as a fundamental condition for sustainable development, and within this framework it provides basic principles of environmental protection, environmental protection measures, monitoring of the state of the environment and information on the environment, economic and financial instruments for environmental protection, public environmental protection services, and other issues related to environmental protection. ^e purpose of environmental protection is to promote and guide the kind of social development that will ensure long-term conditions for human health, well-being and quality of life, as well as the preservation of biodiversity. Nature conservation remains inextricably embedded into the system of environmental protection, through joint planning and programming, joint environmental assessment procedures, joint environmental monitoring, environmental data publicity, access to environmental data, environmental taxes on the use of natural resources, nongovernmental organisations for environmental protection acting in the public interest, and the regulation of concessions on natural resources. ZVO-1 thus provides for a joint national environmental protection programme, which also encompasses a national programme on nature protection. The National Assembly of the Republic of Slovenia adopted the programme jointly with the Resolution on the National Environmental Action Plan 2005-2012 and, based on long-term objectives, policies and biodiversity protection tasks, has drafted an operational programme for the management of Natura sites as one of the key programmes for environmental protection. Operational programmes for environmental protection are identified in Article 36 of ZVO-1. ^ey are adopted by the Government of the Republic of Slovenia (hereinafter: Government) pursuant to the procedure defined in Article 37 of ZVO-1. ^e Nature Conservation Act (Official Gazette RS, No. 96/04 - official consolidated version and 61/06 - ZDru-1; hereinafter: ZON) establishes an integrated system of nature conservation, the purpose of which is the protection of valuable natural features and the conservation of elements of biological diversity. It identifies subjects Í "l'. J!- I'■ -ivV'■■ ■, kl-Jí'- : '.'-S—i "V. of protection; methods and measures for their protection; organisation, financing, programming and planning of nature protection; and other content necessary for effective nature protection. Subjects of protection in biodiversity conservation which are identified or identifiable by area include habitat types whose maintenance at a favourable status shall be given priority, as well as habitats of nationally and internationally protected species, ecologically critical areas and special protected areas (hereinafter: Natura 2000 sites) which form the European ecological network. Subjects of protection also include threatened, protected and internationally protected wild plant or animal species. All subjects of protection are defined under the relevant implementing regulation, act by the minister responsible for nature protection, and Government decree. ZON defines Natura 2000 sites as ecologically important areas which on the territory of the EU are relevant for the maintenance or attainment of a favourable status for birds (special protected areas) and other plant or animal species, their habitats and habitat types (special areas of conservation). Due to a different procedure for designating the areas, special protected areas are already referred to as Natura 2000 sites in the Government decree. Until the European Commission adopts a decision on which special areas of conservation would form the European ecological network in an individual biogeographical region, special areas of conservation shall under national legislation be defined solely as potential special areas of conservation, or potential Natura sites. ^e Natura 2000 sites form the European ecological network called Natura 2000. ^ey are designated by the Government by virtue of a special decree. ^e protection of special protected areas and potential areas of conservation encompasses the protection of a favourable status of plant and animal species, their habitats and habitat types. It is provided through measures for the attainment of protection objectives (hereinafter: protection measures). Protection measures are considered measures pursuant to ZON and measures pursuant to other regulations that may contribute to the conservation of Natura sites; this includes various forms of contract-based protection (e.g. pursuant to regulations on agriculture) and sustainable management plans or natural resource management. Protection measures are defined on the basis of a special management programme adopted by the Government in the form of an operational environmental protection programme, the content of which, as well as the adoption process, are defined in ZVO-1 (paragraph 2 of Article 33 of ZON). In addition to protection measures, the most important measure for protecting Natura 2000 sites and potential Natura sites is the acceptability assessment of the impact of plans or activities affecting nature, on the protection objectives of the Natura sites. ^is acceptability assessment is stipulated for plans within an integrated assessment of their environmental impact carried out on the basis of regulations on environmental protection, whereas for activities affecting nature, the assessment is performed within environmental protection consent, nature protection consent, permits for activities affecting nature or other permits. ^e assessment is regulated in a more detailed way under ZON (Articles 33a, 101, 101a, 101b, 101c, 101d, 101e, 101f, 104a and 105a), the Decree on Special Protection Areas (Natura 2000 sites) (Official Gazette RS, Nos. 49/04, 110/04) and the Rules on the assessment of acceptability of impacts caused by the execution of plans and activities affecting nature in protected areas » ^ ' • ■ ■ I t^ * r: e (Official Gazette RS, Nos. 130/04, 50/06), and takes place in accordance with the requirements of the Habitats Directive as from the date of Slovenia's accession to the European Union. ^ese assessments are carried out independently of this operational programme (the management programme); for this reason, the procedures connected with acceptability assessment are not part of the programme. ^e Decree on Special Protection Areas (Natura 2000 sites) (Official Gazette RS, Nos. 49/04, 110/04, 59/07) designates special protected areas or Natura 2000 sites, protection objectives in these areas, and protection policies for the conservation or attainment of a favourable status of plant or animal species, or their habitats and habitat types, the conservation of which is in the EU's interest, as well as other codes of conduct for the conservation of these areas. ^e decree also designates potential areas of conservation and the method of their protection. The Decree on Special Areas of Conservation (Natura 2000 sites) specifies how the protection of Natura 2000 sites and potential Natura sites should be planned. ^e planning method is the same for both area types, which is why henceforth in this programme, both the protected areas and the potential areas of conservation are referred to under the term "Natura sites". ^e fundamental planning document is the Natura site management programme. It is intended for the implementation of protection objectives on Natura sites and includes a detailed definition of protection objectives, as well as a definition of protection measures and their implementers, and the financial resources. Protection measures are defined taking into account the characteristics of the Natura site, including the socio-demographic, economic and cultural features, the actual situation in the ecosystem, and the existing and expected endangering factors. Protection measures include: s nature protection measures; s measures of modified use of natural resources serving to attain protection objectives; s measures of modified agricultural practice serving to attain protection objectives; s measures of water management serving to attain protection objectives; and s other measures, should they prove necessary for the creation of a favourable status of plant and animal species and habitat types. The Resolution on the National Environmental Action Plan 2005-2012 (ReNPVO) (Official Gazette RS, No. 2/06) stipulates long-term objectives, policies and tasks in environmental protection, including nature conservation. The resolution is based on the fact that the Natura 2000 network represents the areas most suited to the preservation or attainment of a favourable status of species and habitat types in the interests of the EU, of which Slovenia is a member. It therefore envisages measures for the attainment of such status; these may be measures of nature protection, measures of modified use of natural resources, modified water management or agri-environmental measures. Planning these measures constitutes part of the programme for management of special protected areas, which is an operational nature conservation plan adopted by the Government with the aim of realising the objectives of the national nature conservation programme. The key operational programme for biodiversity conservation, as envisaged by the resolution, is the Natura 2000 site management programme (the operational programme). Its content is defined in general by ZON and the strategy for biodiversity conservation in Slovenia, and in a more detailed way by the Decree on Special Protection Areas (Natura 2000 sites). The Biodiversity Conservation Strategy of Slovenia is a strategic document adopted by Slovenian Government resolution on 20 December 2001, which lays down a series of specific objectives and policies for the 2002-2012 period for the coordinated implementation of measures to achieve the three main objectives of the Biodiversity Convention. These objectives are: s biodiversity conservation, s sustainable use of the elements of biodiversity, s fair and just distribution of the benefits of genetic resources. The Cave Protection Act (Official Gazette RS, Nos. 2/04, 61/06-ZDru-1; hereinafter: ZVPJ) regulates the protection and use of underground caves, protection arrangements, protection measures and other codes of conduct, including the rehabilitation of polluted or damaged caves. The act is mentioned here since many Natura sites have been designated particularly due to species bound to underground caves or a cave habitat type. Underground caves are natural resources of national importance and are owned by the state. ^e provisions of ZVPJ are given priority for underground cave protection, while the provisions of regulations governing nature conservation may be used on a subsidiary basis. From a systemic viewpoint, ZVPJ may be regarded as an act on the protection of one type of natural resources, namely, underground caves. ZVPJ thus provides an obligatory code of conduct on cave management, whereby it considers all possible aspects of human behaviour which might endanger a cave in any aspect of its value. For this reason, the first aspect to be regulated is the discovery of caves and their parts, where special qualifications are required for persons discovering and exploring caves. An obligatory protection regime provides for the possibility of access to a cave, which may be free, controlled or prohibited, depending on the endangerment human presence may inflict upon a cave. ^e protection regime, which regulates the mode of operation in the cave itself, similarly constitutes a system of prohibitions and clearly defined exemptions, largely in the form of special permits. ^e protection regime also includes an obligatory mode of operation in the event that public interests may prevail over the interests of conserving a natural resource and a cave may consequently face destruction. For cave protection particularly, cave protection measures may be introduced; these include custody, security, temporary security and rehabilitation. ^ese are nature conservation measures regulated under ZON, whereby a specially modified and elaborated form of cave custody has been implemented for cave protection. Underground caves may be secured in accordance with the method and procedure under ZON. Additional cave protection through security is justified under the fact that protection regimes pursuant to ZVPJ refer solely to operations in the discovery and exploration of caves, operations in the cave itself and in connection with permits for access to caves. Legitimate use of an underground cave may be exercised only on the basis of a granted concession for cave use, whereas a concession for the supply of drinking water to the population is not necessary. A number of legal provisions are bound to the implementation of such concession, which among other matters also regulate permits for open cave arrangements. 1.2 » PURPOSE OF THE OPERATIONAL PROGRAMME The basic purpose of the operational programme is to detail the implementation of obligations under the protection of special protected areas - Natura 2000 sites for the period 2007-2013, as imposed on Slovenia by the Habitats Directive and Birds Directive (see Chapter 1.1). Slovenia will thus be able to attain one of the EU's objectives, namely, the provision of a favourable conservation status of plant and animal species and habitat types important at the European level. By implementing the operational programme, the Government of the Republic of Slovenia will contribute to attaining sustainable development objectives. ^e operational programme designates protection objectives and measures at Natura sites, as well as the competent sectors and responsible implementers of these protection measures. A further goal in this respect is to enable horizontal links with strategic plans and development programmes. s A detailed definition of protection objectives and measures at Natura sites • define in detail the protection objectives and measures resulting from publicly available resources, to the level of precision permitted by these bases and references; • define the conservation requirements for each individual Natura site (Annex 4.2) as the key information for actors participating in the conservation of these areas; • define direct protection measures for management plans for the protected areas; • define measures of modified use to attain protection objectives in: - exploitation of natural resources, - forest management, - agriculture, hunting and fisheries, - water management; • define other measures, should they prove necessary for the creation of a favourable status of plant and animal species and habitat types. s Designate the competent sectors and responsible implementers of protection measures The goal in designating the competent sectors and responsible implementers of protection measures is to implement protection measures, delegate responsibility and provide for monitoring the implementation of the operational programme, and consequently to ensure the successful attainment of objectives. s Enable horizontal links to strategic plans and development programmes of the Government • prepare an overview of development potential that complements the protection measures, and integrate this potential into other strategic plans and development programmes for individual regions and the Republic of Slovenia as a whole, to provide a basis for drawing EU funds, especially where the obligation to contribute to the conservation of the Natura 2000 network is stipulated as prerequisite in the European legislation, and the basis for the endorsement of plans and programmes drafted by EU institutions (particularly the National Strategic Plan for Rural Development, Rural Development Programme, National Strategic Plan for Fisheries Development, Fishery Development Programme, Programme for Drawing LIFE+ Funds, Operational Programmes for Drawing Structural Funds and Regional Development Funds); • acquire an overview of the development needs for sustainable development on Natura 2000 sites, based on opportunities offered by the Natura sites in Slovenia, and determine a financial framework for financing development projects. Take advantage of the opportunities offered by Natura 2000 sites for local or regional development, jobs and economic growth, taking into consideration the economic, social and demographic features and principles of sustainable development With their characteristics, the Natura 2000 sites contribute to conserving the cultural landscape and highlight development potential (a comparative advantage), particularly of those local communities which in relatively large part lie within the Natura 2000 network. An appropriate regional development policy in these areas could significantly influence high-quality regional development, an objective which is exemplified not least in a number of good practices throughout the EU. Prepare an overview of lacking research projects, expertise and data, to be included in research programmes High-quality and regularly updated data on animal and plant species and habitat types are a prerequisite for rapid and educated decision making, evaluation of planning and implementation procedures, linking to EU financial resources, implementation of cross compliance, and drafting status reports and reports on the direction of sector policy. An overview of research projects, therefore, is a basis for prioritisation in drafting research projects in the areas of biology and ecology, as well as for establishing links among research institutions, public and private institutes and non-governmental organisations. r 1 ^T L 4 1 r- r ur r-' — s • u ' U i ; ■ ■ ' r Jí^ CONTENT OF THE MANAGEMENT PROGRAMME 2.1 » OVERVIEW 2.1.1 » NATURA 2000 NETWORK CONTRIBUTION TO BIODIVERSITY ^e ever greater decrease in biodiversity, which is largely a consequence of human activity, has become a social concern of such proportions that in 1992 more than 150 countries signed the Convention on Biological Diversity. Signatories to the convention (numbering 188 by the end of 2005) and the World Summit on Sustainable Development set a goal to reduce the decline in biodiversity by 2010. EU Member States further committed to not only reduce but to stop the decline by 2010 (Strategy of Sustainable Development, adopted at the European Council in Gothenburg in 2001). ^e Message from Malahide, adopted in 2004 by a wide forum of EU participating actors in nature conservation, set out a number of milestones and steps towards the goal. EU members have established the creation and effective management of the Natura 2000 network as one of their key objectives. Biodiversity is most often manifested in the number of species and habitat types (species vegetation). Experts estimate that the number of known species worldwide is around 1.75 million. In Slovenia about 26,000 species are known. Within nature conservation, it is impossible to consider each individual species and to engage actively in the conservation of each species. Biodiversity conservation therefore concentrates on threatened species, meaning those that face extinction in the coming decades and require greater attention than other species. ^e basic principle of biodiversity conservation is protection in situ. ^is is carried out through conservation of species habitats and habitat types. In the Birds Directive and Habitats Directive, the EU has already defined the threatened species and habitat types in Europe that are of nature coinbservation concern. It also defined those whose long-term existence must be ensured by conserving an appropriate habitat within the selected Natura 2000 network sites. ^ere are 214 such species and 61 habitats in Slovenia, with 35.5 percent of the country's area having been designated for their conservation. ^e Natura 2000 network also contributes to protecting endemic and nationally threatened species. Among the species for which a Natura site has been designated, many are considered ecological specialists or are threatened due to widespread deterioration of their habitat. In areas where such species still appear to an exceptional extent (of population or habitat range), other species of conservation concern (species threatened at the national level and hence included on Slovenia's red list) are usually also present. ^e most salient example are sites designated for the habitat type "caves closed to the public", which include most of endemic cave species. ^e Natura 2000 network thus also significantly contributes to conserving other threatened species, their habitats and habitat types. ^e two directives stipulate that Member States introduce two pillars of obligatory methods for ensuring the survival and reproduction of species and habitat types at Natura sites, namely: s appropriate steps to prevent deterioration of natural and species habitats; and obligatory assessment of plans and projects which are not directly connected with or necessary to the site management but likely, either individually or in combination with other plans and projects, have a significant effect on the area. Slovenia has the highest share of Natura sites among all Member States, and the great majority of these areas show an outstanding conservation status of species or habitat types. Meeting obligations to prevent deterioration is therefore pivotal for fulfilling the requirements and achieving the objective of the directives. To this end, ZON and the Decree on Special Protection Areas (Natura 2000 sites) also provide for the adoption of this programme. As Europe is a densely populated and highly industrialised continent, proper measures to prevent deterioration (within the context of in situ conservation) here are typically carried out as part of the sustainable use of natural resources and space, only seldom leaving the areas to natural succession. "^is objective is feasible solely if in situ conservation and the sustainable use of species and habitat types are an integrated part of the development of economic and social activities affecting species, their habitats and habitat types. Under this operational programme, the aforementioned matters are especially relevant to activities of sustainable use of natural resources which must, where feasible and appropriate, integrate protection measures into suitable sectoral and intersectoral plans, programmes and policies. The efficiency and effectiveness of measures to prevent deterioration at Natura sites decisively improve the provision of knowledge and information at all levels. Knowledge and information are crucial in deciding on the most appropriate measures (including sustainable use) to ensure the survival of species and habitat types at Natura sites and the development of individual activities affecting biodiversity, as well as on measures implemented by broad target groups; they are further crucial for education and awareness raising in different target groups. Appropriate methods of disseminating knowledge and information are likewise crucially important. 2.1.2 » NATURA 2000 NETWORK STATUS Slovenia is one of the richest countries in terms of biodiversity - a fact supported by numerous national and international studies. Diversity is also manifested in the extremely high share of territory included in the Natura 2000 network. A survey of the status of bio- and landscape diversity, however, confirms the presence of European trends in threats to biodiversity, albeit they are less pronounced than in other Central European countries. For example, 10 percent of ferns and flowering plants and 56 percent of vertebrates (mammals, birds, reptiles, amphibians and fish) are endangered. The most endangered habitat types are subterranean, coastal and marine types, standing and running waters, and dry and wet grasslands. Endangerment largely results from two causes: loss of habitat and direct increase in the mortality of specimens. To prevent loss of habitat, the basic principle of biodiversity conservation is protecting the ecosystems and natural habitats in situ. This is effected through the conservation of ecosystems or habitats of such species which require greater care than others. In the Birds Directive and Habitats Directive, the EU has already determined species and habitat types that are considered threatened at the European level, and how ways of their conservation within the Natura 2000 network. Hand-in-hand with this, reducing direct types of mortality is carried out jointly with species protection. In most EU member states the Natura 2000 network has now been established and covers the best conserved habitats of threatened species or habitat types at the European level. As part of the designation of Natura sites in Slovenia, the hitherto most comprehensive assessment of the status of these species and habitat types, as well as of the condition of individual outstanding areas, has been prepared. ^is assessment provided the basis for the document at hand, particularly as regards the expert groundwork for designating Natura sites.3 ^e overview is partly based also on other relevant references (for a full list of references, see Annex 1.) Forests cover 71 percent of Slovenia's Natura 2000 network, a figure which is around 15 percent higher than the European average and generally highlights their good condition. In spite of this, some forest types, particularly the lowland floodplain forest, have been considerably grubbed in the past and their condition, therefore, is not considered favourable. As regards non-forest areas in the Natura 2000 network, around 20 percent of these are classified as in-use agricultural areas, the most important among them being the extensive meadows. In many areas their condition is good or exceptional compared to other EU members. However, the pressures threatening their exceptional status are great; they are manifested in a natural way in overgrowth due to the cessation of farming and intensification of their use. Caves play an extremely important role in the Natura 2000 network, as they are subject to conservation in more than 70 areas (from a total of 260). Continental waters represent just over 1 percent of the total area of the network, but their importance to the condition of the network is nevertheless vital. A large part of our waters do not show an outstanding state of conservation. Furthermore, human dwellings are important for the reproduction, staging and hibernation of certain species; hence built-up areas are essential within the Natura network as well. ^is particularly concerns bird (e.g. white stork, Eurasian scops owl) and mammal (e.g. bat) species. 2.1.3 » IMPACT OF ACTIVITIES ON THE ATTAINMENT OF OBJECTIVES IN THE NATURA 2000 NETWORK Implementation of the objectives from the directive on Natura sites (favourable state of species and habitat types) is also tied to the existence and sustainable development of activities, particularly agriculture, forestry, water management, hunting, fisheries and others. Within sustainable development of these activities, this programme sets objectives for the conservation of outstanding conservation status and measures for attaining detailed protection objectives at Natura sites. Some activities may even serve for marketing unspoilt nature (biodiversity), including Natura sites and protected areas, thus producing more added value or new jobs through their activity, especially in tourism and related activities (such as the production of high-quality domestic food and tour guidance). For Slovenia this means a development opportunity, as the country still has a number of relatively well-preserved ecosystems and thus offers the possibility of experiencing and discovering plant and animal species in unspoilt nature. ^e latter is an important marketing element in the tourist offer of rural areas, sought after by a segment of buyers strongly conscious of the value of a 3 An overview of the expert groundwork is available at http://www.natura2000.gov.si/index.php?id=200. healthy environment and the need for its conservation. Therefore, the programme at hand also discusses the sector of sustainable tourism development and is connected with biodiversity marketing at or near those Natura sites which are designated also as protected areas in accordance with the regulations on nature conservation and already have a manager appointed. 2.1.4 » QUALITY OF KNOWLEDGE, DATA AND INFORMATION Knowledge of the state and trends of biodiversity and biology, and ecology of species and habitat types, decisively contributes to suitable measures for their conservation and provides for the appropriate sustainable use of natural resources. The management programme hence includes research activities to establish trends and status. Variable status is asserted within monitoring. In this context, forms of monitoring for establishing the conservation status of species and habitat types are the most relevant. These roughly consist of the extent of areas of distribution, extent of appropriate habitat (including in the foreseeable future), and species population trends or the structure and function of habitat types. In order to establish the efficiency of existing measures and to develop new measures, extensive pilot monitoring of the efficiency of the implemented measures is necessary. To render these and additional data acquired by other sectors usable, they must be converted into electronic form and integrated into a well-organised and publicly available database. The database must be designed so as to provide high-quality data, data sets or derived interpretations for key users. 2.2 » STRUCTURE OF THE MANAGEMENT PROGRAMME The content of this operational programme has been formulated in accordance with the Decree on Special Protection Areas (Natura 2000 sites) which defines the programme's obligatory elements. Essential elements of the programme (including the Natura sites), detailed protection objectives and protection measures are outlined in Annex 4.2 to this programme. The regime for the application of annexes is provided in the text of this programme. Natura sites, as dealt with under this programme, are considered special protected areas designated in accordance with the Birds Directive and potential special areas of conservation designated in accordance with the Habitats Directive. For the aforementioned areas, the operational programme defines detailed protection measures which principally apply to the internal zones of the Natura sites. These measures ensue from protection objectives stipulated under the Decree on Special Protection Areas (Natura 2000 sites) and from the protection objectives for the preservation of habitats of threatened plant and animal species and habitat types, whose maintenance in a favourable state shall be given priority and which are designated in both directives providing for their protection. The objectives for the conservation of species and habitat types at the first level define the desired natural state (area of distribution, extent of habitat, size and structure of the population of species and extent of population fluctuation, structure of habitat types). This desired natural state is conditioned by human (in)activity, for which reason objectives shall be attained through the envisaged and appropriately adapted human activity. The management programme stipulates the measures of modified use of natural resources and other measures up to the level permitted under the legislation in force, mostly by guiding the actions of public services. In this document the detailed protection objectives are defined at such a level so as to promote, through legal instruments and guiding the actions of public services, the desired form of human activity at individual Natura sites. Detailed protection measures, on the other hand, are defined within the framework that has already been laid down in both directives and consequently by their transposition into Slovenian legislation - particularly in ZON and the Decree on Special Protection Areas (Natura 2000 sites). Detailed protection objectives are characterised by varying precision, since knowledge and available information, which determine precision, vary considerably from species to species or among individual habitat types. The programme also defines protection measures and policies for attaining protection objectives, namely, for each particular Natura site separately, whereby the set of measures has been defined with regard to the nature of that particular Natura site. The measures have been defined taking into account the provisions of the directives; these require that Member States define obligatory conservation measures for Natura sites that meet the environmental requirements from the relevant annexes for natural habitat types and species. Therefore, the starting points for determining the measures were the environmental requirements of species and habitat types and, in accordance with the Decree on Special Protection Areas (Natura 2000 sites), the characteristics of the Natura site, the actual status of the ecosystem, and the existing and projected threatening factors, as derived from expert groundwork and references (the publicly available items thereof are listed in Annex 4.1). In the formulation of draft measures for attaining detailed protection objectives, special attention was paid to the legal basis for each measure. To this end, primarily measures with an appropriate legal basis have been cited. Still, some cases have shown that in order to attain the set objectives, measures lacking a legal basis are indeed vital. In such cases, a proposal to adopt an appropriate legal basis has been put forward as a measure. ^e draft measures were subsequently evaluated with regard to socio-demographic and economic characteristics conditioning their feasibility. Based on the accessible data, a general survey of the available (human and financial) resources was carried out; the ambitions to implement the objectives, stemming from the existing legislation and the Government's commitments, were assessed; and the measures were appropriately improved. In accordance with the Decree on Special Protection Areas (Natura 2000 sites), protection measures, as applied to individual Natura sites, are divided into: s nature protection measures; s measures of modified use of natural resources serving to attain protection objectives; s measures of modified agricultural practice serving to attain protection objectives; s measures of water management serving to attain protection objectives; and s other measures, should they prove necessary for the creation of a favourable status of plant and animal species and habitat types. ^e operational programme also defines indicators that must be regularly monitored in order to establish the effectiveness of measures with regard to attaining a favourable status of plant and animal species, their habitats and habitat types. It also evaluates the protection measures and activities necessary to ensure the coherence of the European ecological network. It further determines research activities in the basic and applied sciences that are indispensable to improving knowledge of the ecology of plant and animal species and habitat types. ^e operational programme covers the period 2007-2013. ^e legislative and financial framework for a number of essential measures has slightly changed in 2007, but will henceforth remain unchanged until 2013. Namely, the legislative framework defines the rules for financing measures (regulations providing for drawing EU funds). Namely, the financing for a large number of measures is provided by EU funds. All regulations which include implementing rules for drawing funds from the new financial perspective are expected to be adopted within the first half of 2007. Each financial perspective also envisages a midterm review of the attainment of objectives and, where necessary, an adjustment of the rules for financing. ^e management programme therefore covers the time period until 2013; however, should the financial perspective and the implementing regulations for drawing EU funds be modified in 2010, the programme itself will have to be adjusted as well. 2.3 » DETAILED PROTECTION OBJECTIVES Annex 4.2 lays down the detailed protection objectives for each individual Natura site. ^e objectives largely relate to the internal zones of Natura sites and derive from protection objectives in accordance with the Decree on Special Protection Areas (Natura 2000 sites). Protection measures and other regulatory content are also defined. ^e Natura sites (special protected areas and potential special areas of conservation) partially overlap. Since only one type of measure may be implemented on one area, the overlapping areas are amalgamated, while the objectives, measures and other regulatory contents of the programme are defined for such amalgamated areas. In Annex 4.2 they are referred to as a "group of sites" and include a list of the sites falling within an individual group. In areas designated for several species or habitat types, the protection objectives are mutually adjusted to the level where they are not contending. ^e Decree on Special Areas of Conservation (Natura 2000 sites) specially designates two areas due to their importance for wintering and migratory water birds. ^ese bird species are enumerated in Annex 2 to the mentioned decree, but their characteristics are relevant to determining protection objectives during overwintering or passage migration. For this reason, these species are designated under Annex 4.2 to the programme, for the areas of the Sečovlje saltpans and the Drava River, as a group of overwintering water birds. ^e group of overwintering water birds at the site SI5000011 Drava comprises the following species: white-tailed eagle (Haliaeetus albicilla), tufted duck (Aythya fuligula), great cormorant (Phalacrocorax carbo sinensis), Eurasian coot (Fulica atra), little grebe (Tachybaptus ruficollis), smew (Mergellus albellus), mallard (Anas platyrhynchos), bean goose (Anser fabalis), pochard (Aythya ferina), great egret (Egretta alba), common merganser (Mergus merganser) and common goldeneye (Bucephala clangula). ^e group of passage migrant water birds at the site SI5000011 Drava comprises the following species: black tern (Chlidonias niger), little gull (Larus minutus), wood sandpiper (Tringa glareola) and ruff (Philomachus pugnax). ^e group of overwintering water birds at the site SI5000018 Sečovlje saltpans comprises the following species: black-necked grebe (Podiceps nigricollis), Eurasian coot (Fulica atra), little egret (Egretta garzetta), black-throated diver (Gavia arctica), dunlin (Calidris alpina), common kingfisher (Alcedo atthis) and wigeon (Anas penelope). ^e group of passage migrant water birds at the site SI5000018 Sečovlje saltpans comprises the following species: Mediterranean gull (Larus melanocephalus), sandwich tern (Sterna sandvicensis), little egret (Egretta garzetta), Caspian gull (Larus cachinnans), ruff (Philomachus pugnax) and great egret (Egretta alba). In certain exceptional cases the habitat type already has a favourable conservation status and is in a state of expansion, thus rendering measures unnecessary. In such case even the protection objectives have been omitted. 2.4 » MEASURES TO ATTAIN PROTECTION OBJECTIVES Some principles hold for all types of measures to attain protection objectives and are summarised in this introduction. Protection measures and their contents are laid down in Annex 4.2 to this programme (in the field "Protection measure"). In accordance with the Decree on Special Areas of Conservation (Natura 2000 sites), the measures are divided by sector: namely, nature protection measures, measures of modified use of natural resources (forestry, hunting, fisheries), measures of modified agricultural practice, and measures of water management (in the field "Sector"). The remaining fields may differ with regard to the Decree on Special Protection Areas (Natura 2000 sites). For nature protection measures, the type of measure from ZON and, in the field "Implementer", the implementer of the measure are indicated, save in cases where under Chapter 2.4.1 the implementer has already been designated for each type of measure pursuant to ZON. A detailed protection policy is given for measures of modified use of natural resources, which is then taken into consideration in drafting the plan. The area of the plan is indicated, while the person responsible for the entry of a measure (detailed protection policies) into the plan for each individual area is designated by sectoral law. For measures of modified agricultural use, the arrangements for ensuring the measures of Axis 2 of the Rural Development Programme for the Republic of Slovenia for the period 2007-2013 are indicated, while under Chapter 2.4.3 individual measures, stated in the field "Protection measure", are specified. For measures of water management, the responsible operators will be designated by sectoral law; hence they are not indicated in this programme. The scope of implementation of each of the aforementioned measures and policies is the whole or partial internal zone of a species or habitat type, in which are located, in accordance with the Decree on Special Protection Areas (Natura 2000 sites), those parts of an area that represent the essential parts of the habitats of individual plant and animal species and individual habitat types, due to which the Natura site has been designated (hereinafter: internal zone). The implementation of proactive measures and policies from this management programme seems reasonable only where it is accompanied by an acceptability assessment of the impact of plans or activities affecting nature for these species or habitat types. ^ese internal zones are designated by entry into the register of areas relevant for biodiversity conservation, which is included in the Environment Atlas of the Environmental Agency of the Republic of Slovenia (hereinafter: EARS). In formulating the measures and policies, one could not avoid elements relevant for attaining detailed protection objectives; these have therefore been included in the already adopted measures or statutory prohibitions and regimes. trough consistent implementation of statutory prohibitions and regimes, no threats to the conservation of the outstanding status of species or habitat types should emerge. "^e state of nature, as described in expert groundwork, may lead to the conclusion that regulation is not implemented satisfactorily in a particular area. To implement a detailed protection objective, enhanced enforcement of these regulations is therefore necessary. When the case is about nature conservation regulations, supervision is substantially carried out in the form of inspection and complemented by immediate supervision. ^e implementers are the competent inspection services and the persons competent for immediate supervision. ^e latter includes nature protection supervision in the protected areas executed by authorised nature protection wardens, and forest supervision carried out by authorised wardens from the Slovenian Forest Service (hereinafter: SFS), as well as voluntary supervision. When the case is about fisheries, supervision is substantially carried out in the form of inspection and complemented by the fisheries watchman service. For supervision of nature protection regulations, Annex 4.2 stipulates the contents of prohibitions, jointly with the area where enhanced supervision must be ensured. Attaining detailed protection objectives of water-bound species and habitat types requires enhanced supervision of fertilisation and the use of plant protection agents on the offshore terrain at all Natura sites designated for water-bound species and habitat types. 2.4.1 » NATURE PROTECTION MEASURES Nature protection measures are activities implemented by a country with the view of attaining a detailed protection objective at Natura sites. ^ey are systematically regulated under ZON (contractual protection and stewardship, temporary protection, protection by establishing a protected area, marking on the site, viewing and visiting restriction) and the Decree on Protected Wild Animal Species (restriction of activities threatening protected animal species). Nature protection measures are detailed in Annex 4.2 in the field "Sector", under the heading "Nature protection". ^e basic guidance in selecting the type of measure for attaining a detailed protection objective was the relevant legal measures that have already proved instrumental in attaining an objective or have provided an appropriate basis thereof. Namely, the Natura sites have been partially designated on territories where some of the mentioned legal measures are already being implemented to attain other nature protection objectives, but partially also on territories unaffected by such measures. Measures for the conservation of the brown bear are laid down in the Strategy of Brown Bear Management (Ursus arctos L.) in the Republic of Slovenia and will be further clarified in the action plan. ^is observation is stated alongside detailed protection objectives in the relevant areas. In accordance with ZON, the Institute of the RS for Nature Protection (hereinafter: INP) has been drafting expert proposals for protection and other nature protection measures; it also cooperates in implementation of the nature protection measures at Natura sites. 2.4.1.1 » Site protection and temporary site protection measures Existing protected areas On Natura sites or parts of Natura sites which are also designated as protected areas, the provisions from the act on the protected area can be relevant as a measure to attain a protection objective, and such cases have been specially underlined alongside the measure. In Annex 4.2 it may therefore be indicated that a measure is already being implemented and that it is a case of existing protection or existing temporary protection. When a protection instrument stipulates an obligatory management plan for the protected area, this is largely to be understood as additional input for attaining the detailed protection objective. In such cases, the measure also includes a starting point to be considered in drafting a management plan as a protection measure for the Natura site. ^e actor responsible for submitting the management plan to the Government of the Republic of Slovenia is the Ministry of the Environment and Spatial Planning. Under ZON the drafting of these plans has already been designated to the protected area manager, along with technical assistance from the INP, who are thereby also the responsible operators for preparing measures from the operational programme. Table 1: Overview for the adoption of management plans for protected areas Protected areas Triglav National Park Kamnik-Savinja Regional Park Kozjansko Regional Park Ljubljansko barje Landscape Park Goričko Landscape Park Sečovlje Salina Nature Park Kolpa Landscape Park Škocjanski zatok Nature Reserve Strunjan Landscape Park Plan to be adopted in year 2009 2011 2008 2011 2008 2007 2009 2007 date not yet specified Planned protected areas Protection by establishing a protected area is, in accordance with the Resolution on the National Environmental Action Programme, envisaged for some Natura sites. Protection by establishing a protected area includes drafting and adopting an act on protected area, which may additionally contribute to attaining the detailed protection objective by laying down protection regimes and by appointing a manager to implement proactive measures and investments. In such cases, the measure under Annex 4.2 also includes a starting point to be considered in drafting the protection instrument for the Natura site. ^e actor responsible for submitting the proposal of an act on protected area to the Government of the Republic of Slovenia is the Ministry of the Environment and Spatial Planning. Under ZON, drafting the expert proposal for the act on protection is already delegated to the INP, who is thereby also the responsible operator for preparing measures from the operational programme. Table 2: Timetable for establishing the planned new protected areas To be ESTABLISHED IN Ljubljansko Barje Landscape Park 2008 Kamnik-Savinja Regional Park 2008 Pohorje Regional Park 2010 Dragonja Landscape Park 2010 Karst Regional Park / Karst Edge Landscape Park 2012 Contractual protection and stewardship The following set of nature protection measures constitutes contractual protection and stewardship. In such cases a text has been cited alongside the measure that contains the protection elements of the contract. In the case of contractual protection and stewardship, the operator responsible for implementing the measure is the Ministry of the Environment and Spatial Planning (hereinafter: MESP) with the bodies under its responsibility (core MESP or EARS, depending on the division of assignments in the ministry), except in those protected areas that have their own managers, where such measures fall within the scope of the manager's duties (as specially indicated in Annex 4.2). In accordance with ZON, the preparation of an expert proposal for implementing this measure in the special protected area has been delegated to the INP. Each year up to 2013, approximately one seventh of the contracts are to be concluded (the total number is indicated in Table 3), while priorities will be set in the annual programme of the producer of expert groundwork (INP), or, where measures are to be implemented by the manager, in the annual programme of the manager of the protected area. Table 3: Review of planned measures of contractual protection or stewardship and marking on the site for the period 2007-13 Type of measure Stewardship of caves Contractual protection or stewardship Contractual protection of land in agricultural use Designation in nature Manager of the PROTECTED AREA 7 2 (1,200 ha) 6 18 Marking on the site In Annex 4.2, marking on the site is indicated particularly in cases where through such a measure, and consequently by redirecting visitors, the detailed protection objective may be attained. INP is the responsible implementer, except in those protected areas that have their own managers, where such measures fall within the scope of manager's duties. Measures are to be implemented by 2013 at the latest. Viewing and visiting restriction and restriction of activities THREATENING PROTECTED ANIMAL SPECIES The measures of viewing and visiting restriction and restriction of activities threatening protected animal species are indicated in Annex 4.2, particularly for the portions of sites where the presence of a large number of visitors threatens the attainment of protection objectives. This arrangement is necessary in certain cases where risky visiting may pose a threat, especially when it is a matter of increased tourism or recreation activities (alpinism, sport climbing, hiking, water sports, air sports, spelunking and others). In these parts of the Natura sites (Annex 4.2), such arrangements shall be carried out by adopting a relevant provision, while in protected areas this may also be achieved on the basis of an act on the protected area. ^e operators responsible for drafting these acts are designated on the basis of nature protection regulations and are specified here. For underground caves, the text of the measure includes the contents of a cave and cave life conservation, which are important for the conservation of Natura sites. Where the text of the measure includes restrictions on use, the latter refers to visiting with deliberate disturbance of animals living or temporarily abiding in caves, at all stages of their lives (violation of the regime stipulated in Article 18 of ZVPJ). It is carried out by defining the conditions for granting stewardship or concessions for cave management pursuant to ZVPJ. All cave animal species, including all bats, are protected, for which reason the conditions include restrictions on actions threatening protected animal species. In accordance with the expert proposal by the INP, concession or stewardship shall be granted by the end of the duration of the programme for a total of 33 caves. In case stewardship or concession is granted within this period for any of the remaining caves mentioned in Annex 4.2, the measures from this annex shall be included as well. ^e operators responsible for drafting these instruments are designated on the basis of nature protection regulations and are not specified here. Control In Annex 4.2 elements of control (nature conservation and inspection in accordance with the provisions of ZON) are indicated for some areas, as described in Chapter 2.3. Financial resources Financial resources may vary considerably with regard to the type of nature protection measures. A major set of measures is carried out through the drafting and adoption of acts, accompanied by administrative costs to the existing public administration. Within nature protection measures, these costs particularly include: s establishment of new protected areas; s adoption of management plans for protected areas; s granting of concessions for the permitted cave use; s drafting and signing of contracts on protection or stewardship; s adoption of other regulations (viewing and visiting restrictions and restriction of activities threatening protected animal species). Within other measures, administrative costs relate to: s preparation of projects for the implementation of investments from Annex 4.6, which is the responsibility of the manager of the protected area; s monitoring the conservation status of nature (including, among other matters, monitoring the status of plant and animal species, their habitats, habitat types and special protected areas) and management of databases, performed as a public function by the INP; s communication performed in the context of their duties by the MESP, INP, managers of the protected areas, Agricultural Advisory Service within the Chamber of Agriculture and Forestry of Slovenia (hereinafter: CAFS) and the Slovenian Forest Service (hereinafter: SFS). Such cases also mean continued implementation of the existing measures where financial resources already are provided under main programme 1505 - Assistance and Support to Nature Conservation, under several budget items. Under budget items within this programme, €7,579,368 have been provided for 2007 and €6,483,223 for 2008 under items connected with the implementation of measures under this operational programme (all items, save items 2303 Biotechnology and 6169 ZSPJS implementation funds - public institutions). Cave-related measures normally require no intervention. Measures of cave protection and permitted use (where cave status so permits), which serve to attain protection objectives, as well as the method of their inclusion in cave management, are defined within the framework of measures stipulated under ZON and ZVPJ. In such case financial resources are unnecessary and are therefore not indicated. Other costs for the implementation of nature protection measures and other measures are largely connected with the contents mentioned below. In case of successful application, funds for the implementation of investments from Annex 4.6 are envisaged within the framework of the European Regional Development Fund (ERDF), Operational Programme for Regional Potential Development, as well as sets No. 51 Promoting biodiversity and nature protection (including Natura 2000) and 56 Protection and development of natural heritage, totalling €57.3 million for the period 2007-2013. ^e said financial framework is also available for measures of designation in nature. Financing means are also at disposal in axes 3 and 4 of the Rural Development Plan (RDP). For the increased monitoring of nature conservation status and implementation of non-administrative nature conservation measures (funds for contractual protection or stewardship, if not subject to structural funds or RDP) and communication, budget items of the MESP are earmarked for biodiversity conservation and Natura 2000; particularly important are project funds from the LIFE+ programme. ^is is the largest of the sources for monitoring nature conservation status and implementing non-administrative nature conservation measures; for Slovenia, it is expected to contribute an additional €2-2.5 million annually to national budgetary funds. 2.4.2 » MEASURES OF MODIFIED USE OF NATURAL RESOURCES ^e essential activities of modified use of natural resources serving to attain protection objectives are forestry, hunting and fishery. With these activities, the management programme in Annex 4.2 first indicates the sector implementing the measure of modified use of natural resources (forestry, hunting, fishery). One measure of modified use is inclusion of the detailed protection policy from Annex 4.2, first into the INP guidelines (in accordance with point 3 of paragraph 4 of Article 98 of ZON), and subsequently, in accordance with the provisions of Article 97 of ZON, into the natural resource usage plan, by which the policies of the plan, in accordance with sectoral legislation, are more precisely defined or transposed into measures under the plan. The natural resource usage plans, by which the policies or measures are defined in a more detailed way, are identified in the field "Implementer/ responsible holder". The producer of an individual forest management or aquaculture plan from Annex 4.2 is stipulated by sectoral legislation and is also designated by this management programme as the implementer of policies at the Natura site. ^e sustainable management or natural resource management plans defined in Annex 4.3 may be directly connected with or necessary for the protection of designated areas. In the process of verifying plans for which an integrated environmental impact assessment must be carried out, those plans, if they include objectives and measures and policies for attaining protection objectives on the basis of this programme and comply with other statutory conditions, are designated as sustainable management plans or natural resource management plans, necessary for the conservation of a favourable status of habitat types and habitats of species in these areas. ^is is carried out in the process of preparing and adopting these plans in accordance with regulatory provisions. Under this conclusion, such a plan evolves into a plan that is directly necessary for the protection of Natura sites and for which, in accordance with ZON, an acceptability assessment is no longer necessary. ^e plans are based at minimum on the detailed protection policies from Annex 4.2, but predominantly also include the more precisely determined policies and measures stated in the nature protection guidelines. Guidelines may include other content (policies) necessary for attaining the detailed protection objective. Within the seven-year duration of this programme, a situation may arise when, for a certain species or habitat type at a particular Natura site or portion thereof, new data or information may be available before issuing nature protection guidelines, which may derogate substantially from the data and information used in drafting this programme. In such cases, even a policy or measure mentioned in nature protection guidelines may derogate from the one in Annex 4.2, whereby the new data and information must be clarified and the reasons for derogation must be substantiated. Table 4: Overview of adoption of plans of modified use of natural resources Year of ADOPTION 2007 2008 2009 2010 2011 2012 2013 Total 26 22 27 21 19 21 23 159 Water MANAGEMENT 6-year fishery Presumably 26 RGN 14 14 26 2.4.2.1 » Forestry The framework for the measures is the forestry legislation, which provides for the planning and implementation of all necessary measures for ensuring the favourable status of forest habitat types and species bound to forest ecosystems. Detailed protection policies for the modified use of forests (natural resources) serving to attain protection objectives are indicated by area in Annex 4.2. Plans with jurisdiction to define the implementation of these measures are designed in accordance with forestry regulations and forest management plans. These unit plans (GGE) are defined in Annex 4.3, jointly with the envisaged year of adoption. Seventy-one plans from the mentioned annex were adopted in the period 2004-2006, and these unit plans will continue to be adopted in a regular procedure after the operational programme expires. In the areas of forest management units covered by these plans, measures of modified use of forests (natural resources) serving to attain protection objectives with detailed protection policies may be integrated upon the adoption of GGO area plans. The adoption of area forest management plans is expected to take place in 2011. In areas where the annex so states, in the preparation of forest management plans the policies from Annex 4.2, referring to the leaving of the dead woodmass in forest, are provided in accordance with the Rules on the Protection of Forests. The producer of an individual forest management plan from Annex 4.3 is stipulated under the forestry regulations and is also designated by this management programme as the implementer of policies or measures at the Natura site. The costs for preparing management plans by the competent public authorities (SFS, Fisheries Research Institute of Slovenia) and drafting nature protection guidelines and opinions (INP), as well as the procedures of their adoption, are of an administrative nature. 9 2 9 2 Map 1: Overview of GGE plans serving to attain protection objectives. Year of adoption of the plan: 2007 2008 2009 2010 2011 2012 2013 ^e white colour marks the plans of forest management units, according to which measures are to be included in area plans for 2011. Source for GGE delimitations: Slovenian Forest Service. For some time forestry legislation has also been providing for the implementation of measures for attaining the protection objectives of forest species and habitat types at Natura sites. Enforcement of the legislation is bound to financial means available for promoting these measures; in the coming years, therefore, it seems reasonable to increase these funds. 2.4.2.2 » Hunting There are relatively few hunting-related objectives on the Natura sites. They are attained through the modified use of wild game (a natural resource) as governed by regulations on wild game and hunting. ^e activities of wild game habitat management at numerous Natura sites contribute to attaining protection objectives related to agriculture, forestry, water management, etc. Detailed protection policies of modified wild game use are defined for individual Natura areas in Annex 4.2. Plans with jurisdiction to define measures as a form of implementing these policies are, in accordance with forestry regulations, designated as plans of wild game management and are defined in Annex 4.3. ^e producer of an individual wild game management plan from Annex 4.3 is stipulated under the hunting regulations and is also designated by this management programme as the implementer of policies or measures at the Natura site. 2.4.2.3 » Fishery Fishery activities comprise freshwater and marine fishery. Freshwater fishery means fishery resource management in continental waters. Commercial fishing for the market is carried out exclusively in marine waters and aquaculture, namely within the EU Common Fisheries Policy (CFP). ^e great majority of this activity takes place outside the Natura 2000 network. Fishery as the sustainable use of a natural resource, on the other hand, is carried out in the majority of watercourses forming part of Natura sites. It is governed by regulations on freshwater fishery, which, among other things, require the adoption of a programme and plan of management of fish as fishery resources. Policies of modified use of fishery resources (natural resources) are defined for individual Natura sites in Annex 4.2. Plans with jurisdiction to define measures as a form of implementing these policies are, in accordance with fishery legislation, designated as plans of fishery management in a fishery zone and aquaculture plans for fishery environments. ^ese plans are defined in Annex 4.3. ^e producer of an individual plan of fishery management in a fishery territory or an aquaculture plan from Annex 4.3 is stipulated under the fishery regulations and is also designated by this management programme as the implementer of measures at the Natura site. 2.4.3 » MEASURES OF MODIFIED AGRICULTURAL PRACTICE At many Natura sites, the implementation of agricultural activities is a prerequisite for preserving the outstanding conservation status of certain species and habitats. In accordance with the regulations in force, sustainable use of agricultural land is not regulated in the form of planning use through the adoption of appropriate management plans. For these farmlands, different instruments for regulating agricultural use exist. In general, the most important method of applying agricultural activity into individual farming models is based on appropriate programmes within the framework of financial incentives of the EU Common Agricultural Policy. These programmes are intended to ensure food production and other functions of agriculture, particularly within the 2007-2013 Rural Development Plan (hereinafter: RDP). Financial incentives within measures of Axis 2 from the 2007-2013 RDP of the Republic of Slovenia have been allocated in accordance with the farmer's voluntary decision to accept a commitment (eligibility) to fulfil the requirements of a measure on the eligible land for five years. Within the context of nature protection measures, this commitment by a farmer also satisfies requirements for measures of contractual protection pursuant to other, namely agricultural, regulations. ^e operational programme includes measures of modified agricultural use which ensure the outstanding conservation status of species and habitats, and are subject to integration into appropriate agri- environmental measures designated for individual Natura sites in Annex 4.2. ^e area of implementation of each mentioned measure is either the entire or partial internal zone of a species or habitat type. ^e proposed measures relating to agriculture include agri-environmental measures from the 2007-2013 RDP (indicated in Annex 4.2 with the abbreviation "KO programme"). Abbreviations in Annex 4.2 refer to the following measures or submeasures: s s s s EKS is the joint code for any of the measures which, through their requirements, ensure conservation of permanent grassland, namely 214-I/7 Organic farming - Permanent grassland (EK T), 214-II/1 Alpine grazing (PP or PPP), 214-II/2 Steep meadow cutting (S35 or S50), 214-II/3 Hummocky meadow cutting (GRB), 214-II/7 Sustainable domestic animal husbandry (REJ), 214-II/8 Conservation of extensive grassland (ETA), 214-III/2 Conservation of special grassland habitats (HAB), 214-III/3 Conservation of grassland habitats of butterflies (MET), 214-III/4 Conservation of litter meadows (STE), and 214-III/5 Provision of favourable status of populations of threatened bird species and humid grassland habitats (VTR). HAB signifies measure 214-III/2 Conservation of special grassland habitats, or measure 214-III/5 Provision of favourable status of populations of threatened bird species and humid grassland habitats (VTR). MET signifies measure 214-III/3 Conservation of grassland habitats of butterflies (MET). STE signifies measure 214-III/4 Conservation of litter meadows (STE). VTR signifies measure 214-III/5 Provision of favourable status of populations of threatened bird species and humid grassland habitats (VTR). TSA signifies measure 214-II/4 Meadow orchards (TSA). EK SD signifies measure 214-I/7 Organic farming - orchards (EK SD). Implementation is carried out though measures of Axis 2 of the 2007-2013 RDP of the Republic of Slovenia. Funds from the RDP are allocated for their enforcement in the respective period. In the same way, the objective from the national environmental action programme (hereinafter: NEAP) is attained: The integration of as large a zone as possible of areas relevant for the conservation of biodiversity into the implementation of (from the viewpoint of maintaining the favourable status of species and habitat types) appropriate agri-environmental programmes. Table 5: Funds for participation in agri-environmental measures Amount of annual funds for SKOP measures in the Natura site zones Status in €2.4-2.7 mio ca. €2.5 mio ca. €2.5 mio Objective FOR 2010 €2.5-2.7 mio ca. €2.8 mio ca. €3.0 mio Objective FOR 2013 €3.2-3.4 mio The status of agri-environmental measures in 2005 is based on an analysis of integration into agri-environment measures on an individual Natura site designated for cultivated species or habitat types. The 2005 financial estimate is based on the approved agri-environment measures (no appeals) and the amount of payments 2005 determined by the Government decree for 2005. Disparities in the amount of funds occur because it is impossible to determine exactly from which initial agri-environment measures in 2005 farmers would progress to target agri-environmental measures in 2010. Some of the initial agri-environment measures presuppose higher payments than the target agri-environmental measures. Despite greater integration into target measures, however, a considerable increase in the total range of payments per area by 2010 is not expected. Evaluation of resources necessary for the attainment of the objective in 2010 is based on the scope of objectives laid down in the annex to the operational programme and the amount of payments designated by the Government decree for 2007-2013. The integration of territories into these measures is linked to the appropriateness and attractiveness of the amount of payment for an individual measure; the latter, however, is also connected to the financial resources available for the programme. In the coming years it seems reasonable to increase resources for these purposes of the programme. In the parts of meadow zones where physical conditions prevent overgrowth (e.g. above the timber line), modified agricultural use is not necessary. ^e method of ensuring modified agricultural use on state-owned land within the protected areas may also be based on an agreement between the Farmland and Forest Fund of the Republic of Slovenia and the ministry responsible for nature protection or the manager of the protected area. ^ere are more than 50,000 ha of lands on the Natura sites which still exist as meadowlands or have existed as meadowlands in the recent past and are not subject to active agricultural use (meaning, they receive no state support). Overgrowth is already appearing on these lands. Ecological requirements of species for which these areas have been designated postulate that these areas represent their habitats only until overgrowth is completed. On many Natura sites, properly modified agricultural use of these lands may provide for the outstanding status of species and habitats. A majority of these lands are to be found in areas which are simultaneously classified as less favourite areas (OMD). Consequently, their revival depends on available funds for the payment of OMD within the 2007-2013 RDP, for which reason within the framework of measures it is limited collectively to less than 10,000 ha by 2013. 2.4.4 » WATER MANAGEMENT MEASURES Water management is important for conserving biodiversity and attaining the favourable conservation status of Natura sites. ^ere are 110 species and habitat types which depend on water for the provision of favourable conservation status. ^ese are species which spend part of their annual or life cycle in or near water for reproduction, feeding or overwintering, and habitat types bound to the constant presence of (underground or surface) water. ^ey are primarily influenced by changes in the hydromorphological characteristics of surface waters and changes in the quantitative and chemical status of underground waters. ^e National Assembly of the Republic of Slovenia has adopted a national water management programme; for its implementation, the Government is expected adopt a water management plan (hereinafter: WMP) for the Danube and Adriatic watersheds, plus a programme of measures. Above all, the WMP will contain an evaluation of the status of water bodies and, taking into account possible exceptions, lay down objectives for attaining the good status of bodies of water. For the attainment of these objectives, the programme of measures will define water management measures, defined by the regulations on environmental protection, and additional measures necessary for attaining the good status of bodies of water; in this regard Natura sites, as designated by the regulations on nature conservation, will be treated as areas with special requirements. From the methodological view, part of the environmental requirements of a species or habitat type at each Natura site will be comprised within the framework of the good environmental status of waters. ^is means that they are integrated into the WMP objectives and the measures to attain objectives from the WMP; where necessary, they are also integrated into the programme of measures in accordance with the Waters Act. Possible specific environmental requirements not comprised within the framework of the good environmental status of waters shall be defined in an appropriate act or programme. ^erefore, for water management, Annex 4.2 contains the framework of environmental requirements of species or habitat types integrated into the relevant parts of WMPs by applying nature protection guidelines, as the text of the detailed protection policy to attain detailed protection objectives in water management. ^e mentioned plans include the WMP and the programme of measures; where detailed WMPs are adopted, the latter are also taken into account. In accordance with the timetable laid down by the Water Framework Directive 2000/60/EC, these acts and other implementing regulations will be first adopted in 2009. Other measures based on regulations on environmental protection are already being implemented in accordance with the operational programmes. ^e objectives of the management plan and the objectives of other operational programmes, based on the environmental protection regulations laid down by the NEAP or by a national water management programme adopted within the framework of the former, shall contribute to the good status of water which underlies the conservation of the favourable status of habitat types and species at Natura sites. Where necessary, detailed WMPs shall also contribute to the conservation of a favourable status of habitat types and species. ^e area of implementation of each mentioned measure is either the entire or partial internal zone of a species or habitat type. 2.4.5 » OTHER MEASURES Other measures, should they prove necessary for the creation of a favourable status of plant and animal species and habitat types, refer particularly to regional and tourism development, status monitoring, communication, education and training. 2.4.5.1 » Measures of sustainable development aimed at direct benefits from Natura sites for the local population ^e sustainable development of regions and the development of tourism and other entrepreneurial opportunities is connected to sustainable biodiversity management, including marketing and providing long-term biodiversity conservation. Sustainable regional development additionally requires developing qualified and motivated human resources for the advancement of services which in such an environment could flourish in a more competitive way. For the sustainable development of regions, the management plans of protected areas primarily take into account the following scopes: s Infrastructure for visiting protected areas (information centres, lookout spots, designations, footpaths, natural science paths, cultural paths, educational paths). Marketing biodiversity through tourism requires certain investments into tourist infrastructure and nature interpretation (or park) infrastructure (e.g. educational or adventure trails, information centres). Such infrastructure attracts visitors and tourists, helping them to experience nature or to come into contact with animals and plants. By offering such adventures, an area may become a popular tourist or vacation destination. A well-planned park infrastructure also directs visitors to specific areas of nature (Natura sites), thus helping them to "concentrate" on particular spots or surroundings of the Natura sites where local products may be marketed (agricultural products, souvenirs, hospitality services and the like). At the same time, they should be diverted from sensitive areas of nature, where large numbers of visitors may prove detrimental to attaining protection objectives. s Identification of new and area-specific entrepreneurial opportunities with regard to the identified potential of an area (assistance to enterprises and e-companies linked with sustainable development, laying particular emphasis on entrepreneurial initiatives for promoting renewable energy sources, efficient energy use and sustainable mobility). s Drafting a concept and building an infrastructure of sustainable mobility and other supporting public infrastructure in the area. This includes drafting a territorial concept of sustainable (or soft) mobility, with an emphasis on public passenger transport, cycling routes and footpaths, and the spatial siting of intermodal points for traversing between different transport modalities (including car parks, public toilet facilities and other supporting infrastructure). Concepts of sustainable mobility are oriented towards calming traffic, directing passengers to public transport and using low- or zero-emission and silent modes of transport. s Development of complementary activities on farms with identified measures for human resource development (organic farming, traditional and alternative medicine, souvenirs, home sales, handicrafts and art crafts, social farm holdings, ecotourism and the like), and introduction of flexible types of work, including telework. s Development of new tourist products Measures which contribute decisively to the above described forms of orienting visitors are the preparation and implementation of investments, including services, into the aforementioned scopes. Investments and services from Annex 4.6 shall also be financed by funds from the structural funds of the new financial perspective. Possible resources are indicated alongside each investment. These resources enable drawing funds in the form of projects. Investments and services are primarily centred on the existing protected areas, which may include Natura sites and already have a manager appointed, and on the planned protected areas whose managers will be designated during the duration of the operational programme. Set A of Annex 4.6 shows the range of investments considered as the national programme of investments and services tied to the development of park infrastructure for the advancement of tourist offers in the protected areas. Part of these investments may, in accordance with the resources available for these purposes, be co-financed within the framework of the Operational Programme for Strengthening Regional Development Potential: development priority 3.5.3 Linking natural and cultural potential, and priority policy 3.5.3.1 Increasing the competitiveness of the tourist economy. The range of investments to be co-financed within the framework of this priority policy and the 2007-2011 Development Plan and Policies of Slovenian Tourism will be agreed between the Ministry of the Economy and the Ministry of the Environment, Spatial Planning and Energy. Local communities or their authorised institutions may apply with portions of investments and services tied to resources from the structural funds, within the framework of the Operational Programme for Strengthening Regional Development Potential, programme 3.5.4 Development of regions. Projects shall be endorsed by regional councils. On drafting this operational programme, a list was produced containing project proposals (types of investments and services) that may contribute to the conservation of Natura sites and increase their potential for tourist and regional development. For Natura sites which are simultaneously classified as protected areas with managers appointed, this range of project proposals from Annex 4.6 is listed in Set B. For Natura sites which are not classified as protected areas with managers appointed, a more general range of proposals is indicated in Set C of the same annex. Managers of the protected areas are responsible for actively proposing projects from Set B of Annex 4.6 to applicants, or for responding to proposals put forward by applicants. In addition, local communities are invited to refer to sets B and C and to prepare projects to apply for funds from the Operational Programme for Strengthening Regional Development Potential or funds from axes 3 and 4 of the 2007-2013 RDP. 2.4.5.2 » Monitoring For monitoring indicators under this programme (see Chapter 3.2 to learn more), more precisely: s indicators of the status of species and habitat types (particularly examining changes in the natural range and population dynamics of species or territory covered by the habitat types); and s indicators of monitoring the implementation of measures; and for briefing the EU and bodies under international conventions and agreements, it is necessary to monitor nature conservation status in accordance with Article 108 of ZON (monitoring the conservation of nature). In Slovenia the monitoring of particular species is carried out; however, the monitoring of a number of species and habitat types that are subject to conservation at Natura sites is yet to be implemented. Taking into account the large number of species on one hand, plus the staff and financial restraints on the other hand, the introduction of monitoring will be gradual. In the initial stages, therefore, it is reasonable to monitor the status of particular species through indirect parameters. ^e number of collected data on species and habitat types has been rising from one year to the next, and their applicability is inseparably linked to electronic format and integration into a well-organised and interconnected database which should be adapted to its key users. In regard to indicators, a well-connected and organised database should therefore be established and managed, which provides its key users data, data sets or interpretations derived from these data. Pursuant to ZON, the INP shall manage databases on valuable natural features and components of biological diversity. An urgent step in establishment of the database is to lay down technical standards for collecting and entering data, which would provide for their interoperability in the base. To fill the base with data, the following points are also relevant: s to digitalise relevant older data in non-electronic form; s to establish mechanisms for stimulating field compilation of relevant data; s to establish mechanisms for stimulating incorporation of data, particularly those compiled through public funds, into the database. Considering foreign experiences (e.g. British NBN, Swedish Artportalen, etc.), the most difficult part of developing computer technologies is reaching an agreement with data producers on how to obtain high-quality data and to incorporate them into a centrally accessible database, plus reaching an agreement between data producers and users on the form of these data. 2.4.5.3 » Communications In the period 2002-2004, with the Natura 2000 network, a comprehensive communications project was prepared and carried out under the guidance of MESP which - on the necessary condition that appropriate mechanisms be established to attain the protection objectives of the Natura sites - gave highly positive results. ^e project was based on communications among public services (especially INP, park managers, SFS, and the Agricultural Advisory Service within CAFS), with the support of nongovernmental organisations engaging in nature conservation. ^e project also offered rather well-defined starting points for further communication. In 2005 management was fully delegated to the INP. Since the second half of 2006, a comprehensive communications project has been underway as a support to biodiversity conservation. ^ese actions also contribute significantly to the implementation of the operational programme at hand, and within their framework a communications strategy proposal will be put forward in 2007. Successful and efficient communication is expected to play a crucial role in the actual attainment of the set objectives and measures. ^e adoption of a communications strategy will therefore be one of the key steps in enforcement of the operational programme. One specific element of communication is reaching an agreement on implementation of a measure which requires altered behaviour of a specific target group (e.g. climbers, hikers, sport sea fishermen) to attain the detailed protection objective at certain Natura sites. For this reason, a text has been cited in Annex 4.2 alongside the measure that contains the protection elements of the agreement on implementing the measure. Within the context of raising awareness on the importance of nature conservation, this is the responsibility of the INP (point 3 of paragraph 3 of Article 117 of ZON). 2.4.5.4 » Education and training Education and training are oriented towards two major target groups: s professional services and NGOs engaging in biodiversity conservation and management of the elements of biological diversity; s the entire population participating in regular educational programmes, with particular emphasis on higher education and university programmes (education and science). Preparation and implementation of a regular educational seminar is a key task for professional services and NGOs. To improve knowledge of the second target group, the appropriate measure is the insertion of basic and applied nature protection content into all education programmes, particularly at the college and university levels (education and science), resulting in an increased number and improved quality of appropriate teaching programmes. Improvements to and expansion of the nature protection profession at the university level will also be necessary (nature protection chair). ^e objective is to increase the share of the population with a positive attitude towards biodiversity, with emphasis on the Natura 2000 network. SUPPORT ACTIONS FOR EFFECTIVE MANAGEMENT OF THE NATURA SITES 3.1 » COHESION OF THE EUROPEAN ECOLOGICAL NETWORK ^e cohesion of the European ecological network and satisfactory integration of the Slovenian Natura areas into the European Natura 2000 network is the responsibility of the European Commission. The established procedure in this regard comprises biogeographical seminars, where additional obligations for Member States are determined in negotiations between that state and the Commission. Slovenia has already completed these seminars and negotiations, and should now enforce the adopted decisions to provide for satisfactory cohesion and conformity of the European ecological network. A regulation should be adopted to complement the annex to the Decree on Special Protection Areas (Natura 2000 sites) qualifying species and habitat types at the designated or proposed Natura sites; also, additional Natura sites should be proposed or the delimitations of some existing Natura sites should be corrected. 3.2 » INDICATORS AND MONITORING OF THE ABOVE In accordance with the indicators under the NEAP, which should regularly be monitored in order to establish the efficiency of measures to attain the outstanding status of plant and animal species, their habitats and habitat types, two types of indicators exist. ^e first type are indicators of the status of species and habitat types, intended particularly for providing data for the examination of changes in the natural range and population dynamics of species or territory covered by the habitat type. Taking into account the large number of species on hand, and the staff and financial restraints on the other hand, a selection of indicators has been made. ^ese indicators are defined in Annex 4.5 and are used in connection with detailed protection objectives for an individual special protected area. Wherever it proved possible with regard to the level of knowledge, the detailed protection objectives have been laid down so as to be expressed by means of the size of population or the range of territory of a habitat type. Certain types of monitoring are already underway; they have been marked in Annex 4.5 as "implemented". Other species or habitat types for which monitoring has not yet been effected, but which permit monitoring in respect of their identification in the country, have been marked in the same annex as "to be established". ^e deadline for establishing the monitoring of status or monitoring with regard to the mentioned indicators is 2010 at the latest; by that time, the results of the status monitoring will be necessary for a mid-term evaluation of the attainment of objectives. In the annex, species monitoring is classified into groups with respect to their characteristics. ^e designation "target monitoring" includes the group of species which, due to their ecological and biological traits (particularly distribution, connection to small-scale habitats, specific detectability, difficult determination and the like), allow for credible data on the size of populations and trends to be acquired solely by applying methods specifically adapted to their ecology and biology. ^e designation "winter counting of water birds" comprises all overwintering water birds. ^is type of monitoring is additionally adjusted to assessing the global size of water bird populations and is carried out concertedly worldwide in accordance with international agreements. The designation "general monitoring" includes the group of species which, due to their ecological and biological traits, allow for sufficient data on population trends to be acquired by applying the method of general census on a raster net, as proposed by Ferlin 2004. The designation "monitoring on agricultural lands" encompasses the group of bird species which, due to their ecological and biological traits, allow for sufficient data on population trends to be acquired by applying the method of general census on special point nets. This type of monitoring is additionally adjusted to assess the effects of the Common Agricultural Policy and is part of the pan-European monitoring of the bird index (bird index of the agricultural landscape). The designation "monitoring of watercourses" embraces the group of water species for which, due to the method of sampling (electrodepletion), sufficient data on the size of populations and trends may be acquired by appropriately dividing watercourses into sections. The designation "detection of presence" covers a group of little-known species (as concerns their range), for which reason satisfactory monitoring cannot be established using the existing knowledge. The designation "forest monitoring" indicates forest habitat types, the monitoring of which may be implemented within the existing forest monitoring. The designation "habitat type mapping" indicates non-forest habitat types, for which monitoring may be provided by modified habitat type mapping. The second type are indicators of monitoring the implementation of measures. Wherever it has proven possible with regard to the level of knowledge, measures have been laid down so as to be measurable. These indicators, too, have been defined in the measure itself. Here is an example: in the internal zone of the Marsh Fritillary, regular and extensive mowing or grazing helps to preserve the extent of meadowlands; proper use is ensured through agri-environmental measures and measures of extensive meadow use, namely at 25 ha by 2010 and at 45 ha by 2013. The indicator of implementation of the measure, therefore, is 25 ha under measures by 2010, or 45 ha under measures by 2013. Monitoring the conservation status of nature includes, among other things, monitoring the status of plant and animal species, their habitats, habitat types and special protected areas (Article 108 of ZON). The management programme thus provides only a detailed account of the animal and plant species and habitat types subject to conservation on Natura sites. ZON also stipulates that the INP performs, as a public service, monitoring of the status of nature conservation and monitoring of the status of biodiversity; in this way, the implementer has already been designated. The service is funded from financial resources which have not been addressed specially under the management programme. Certain types of monitoring are already underway; they have been marked in Annex 4.5 as "implemented", and the financial resources for them have already been endorsed. During the new financial perspective, the EU will provide an important financial resource, the LIFE+ financial instrument, which, even more directly than in the past, will target the financing of monitoring. For the purposes of assessing the adequacy of implementation of measures, more comprehensive monitoring in the pilot areas should be encouraged in addition to the mentioned monitoring. Conclusions derived solely from the aforementioned monitoring may prove false. Introducing respective pilot monitoring is reasonable after the areas of implementation of measures have been specified. To better understand the interaction of human impact on nature, indicators of key anthropogenic impacts (both positive and negative ones) relating to conservation status should be determined. In most cases this means indicators developed by the European Environment Agency within the SEBI project. For other non-SEBI indicators as well, the sources for determining their values and the method of their monitoring should be ascertained. All indicators should be based on precision, which for Slovenia's needs should manifest the interaction of the anthropogenic impact on nature. Agregated data fulfil requrements to be submitted to EU institutions. It seems reasonable to build on the existing databases administered by the Surveying and Mapping Authority of the Republic of Slovenia, Ministry of Agriculture, Forestry and Food, Statistical Office of the RS and other institutions, and to subsequently integrate the indicators as an upgrade to the existing databases. ^e aforementioned data and the interpretation derived thereof should serve as the basis for the regular production of complex reports to be submitted to international institutions (particularly EU bodies and bodies under international conventions) monitoring changes in the status of Natura species and habitat types, the species and habitat types from the annexes to the Birds and Habitats directives, biodiversity in broader terms, and the effectiveness of measures. Not least, the public, too, has a right to these data, and some participants (e.g. experts and researchers) use it increasingly in order to enhance the quality of their results. 3.3 » RESEARCH AND TECHNOLOGY DEVELOPMENT Analysis shows a chronic lack of synthesis on the status and trends in biodiversity, as well as on the ecology and biology of species and their vegetations. Even more apparent is the lack of synthesis requiring the long-lasting accumulation of knowledge. For this reason, at least in the field of biology, the practical application of knowledge is extremely difficult; the same holds true for the field of biodiversity conservation. ^e first goal of the programme, therefore, is to define research activities in the basic and applied sciences which shall be financed as a priority and are indispensable to improving knowledge of the ecology of plant and animal species and habitat types. The transfer of such knowledge into practice depends on the determination of endangerment and the key sources of endangerment of species and habitats; the latter provides the groundwork for the production of red lists of threatened species and habitat types. ^ese may be linked to the development of technologies (e.g. the use of natural resources) which strengthen the conservation of biodiversity, thus providing for an equal if not even more effective use of natural resources in the coming decades. One goal of the NEAP is to increase the number of research projects carried out to provide knowledge of this field and to make an effective contribution to enhancing the information system for biodiversity conservation. In accordance with the Decree on Special Protection Areas (Natura 2000 sites), this management programme further determines research activities in the basic and applied sciences that are indispensable to improving knowledge of the ecology of plant and animal species and habitat types (Annex 4.4). ^is annex shall be taken into account in the allocation of funds for research programmes and projects, target research projects and other appropriate programmes. For some species and habitat types in individual areas, no measures to attain detailed protection objectives could have been proposed on the basis of the existing resources, nor could any detailed protection objectives have been set. Such species and habitat types are listed in Annex 4.7. For these, minor target research studies should first be performed, the results of which would subsequently be used in the next revision of the management programme or in the drafting of a new management programme. ■t A i ^ ^ iA ^. i ^ U 09. ■i -mr^- ÍL- lýjÉT ANNEXES t"».?;. m 4.1 » REFERENCES 4.1.1 » GENERAL REFERENCES Mršić, N., 1997: Biotska raznovrstnost v Sloveniji. Slovenija - "vroča točka" Evrope. MOP, Uprava RS za varstvo narave, Ljubljana. UNEP-WCMC 2001: Global Biodiversity Outlook. Montreal. Williams, P., Humphries, C. & Araujo, M., 1998: Mapping Europe's Biodiversity. V: Delbaert B.C.W. Facts & Figures on Europe's Biodiversity - State and Trends 1998-1999. Wageningen. Kus Veenvliet, J. 2006: Ocena izvajanja Konvencije o biološki raznovrstnosti v Sloveniji. Regionalni center za okolje za srednjo in vzhodno Evropo, Ljubljana. Marega, M. et al. 2006: Krepitev zmogljivosti za globalno okoljsko upravljanje v Sloveniji. Regionalni center za okolje za srednjo in vzhodno Evropo, Ljubljana. Natura 2000 Barometer http://ec.europa.eu/environment/nature/natura2000/barometer/index_en.htm Sklep Vlade RS Načrt ugotavljanja posledic vpliva območij Nature 2000 in določitve razvojnih ukrepov http://www.natura2000.gov.si/index.php?id=140#c163 Report and recommendations on communication (in English) at: http://www.natura2000.gov.si/uploads/tx_library/final_report.pdf T 4.1.2 » GROUNDWORK FOR MEASURES An overview of the expert groundwork is available at http://www.natura2000.gov.si/index.php?id=200 Action Plan for the Conservation of the Italian Agile Frog (Rana latastei) in Europe. Convention on the conservation of European wildlife and natural habitats, Standing Committee 25'h meeting, Strasbourg, 28 November-1 December 2005. Action Plan for the Conservation of the Crested Newt Triturus cristatus Species Complex in Europe. Convention on the conservation of European wildlife and natural habitats. Standing Committee 25'h meeting, Strasbourg, 28 November-1 December 2005. Anthes, N., T. Fartmann, G. Hermann & G. Kaule, 2003. Combining larval habitat quality and metapopulation structure - the key for successful management of pre-Alpine Euphydryas aurinia colonies. Journal of Insect Conservation 7: 175-185. Bachmann, J. 1999. European freshwater species strategy. WWF European Freshwater Programme. Bertok, M., N. Budihna, M. Povž & T. Seliškar, 2003. Strokovne osnove za vzpostavljanje omrežja Natura 2000, Ribe (Pisces), Piškurji (Petromyzontidae), Raki deseteronožci (Decapoda). Zavod za ribištvo Slovenije (Končno poročilo). Božič, L. 2003. Mednarodno pomembna območja za ptice v Sloveniji 2. Predlogi Posebnih zaščitenih območij (SPA) v Sloveniji. DOPPS, Monografija DOPPS št. 2, Ljubljana. Bricelj, M., 2002. Moje tvoje morje: Slovensko Sredozemlje in trajnostni razvoj. Ministrstvo za okolje in prostor Republike Slovenije, Ljubljana. Butaye, J., D. Adriaens & O. Honnay, 2005. Conservation and restoration of calcareous grasslands: a concise review of the effects of fragmentation and management on plant species. Biotechnology, Agronomy, Society and Environment 9(2): 111-118. Crivelli, A., G. Poizat, P. Berrebi, D. Jesensek & J-F Rubin, 2000. Conservation biology applied to fish: the example of a project for rehabilitating the marble trout (Salmo marmoratus) in Slovenia. Cybium 24(3): 211-230. Crofts, A., & R. G. Jefferson (eds), 1999. The lowland grassland management handbook. English Nature/The Wildlife Trusts. Čelik, T., R. Verovnik, S. Gomboc & M. Lasan, 2005. Natura 2000 v Sloveniji. Metulji. Založba ZRC, ZRC SAZU, Ljubljana. Čušin, B. (ur). 2004. Natura 2000 v Sloveniji. Rastline. Založba ZRC, ZRC SAZU, Ljubljana. DOPPS 2004: Monitoring populacij izbranih vrst ptic. Prvo vmesno poročilo - popisni protokoli. Poročilo za ARSO. DOPPS 2005: Kosec (Crex crex) Vrstni akcijski načrt 2005-2015. Poročilo za projekt LIFE. DOPPS 2005: Integrating NATURA 2000 Requirements into the National Rural Development Programme (2007-2013). Republic of Slovenia. September 2005. Poročilo za Farming for Life Campaign. DOPPS 2006: Strokovna izhodišča za vzpostavljanje omrežja Natura 2000 predlogi posebnih varstvenih območij - del po direktivi 79/409/EEC - notranja conacija habitatov kvalifikacijskih vrst ptic. Drovenik, B. & A. Pirnat, 2003. Strokovna izhodišča za vzpostavljanje omrežja Natura 2000. Hrošči (Coleoptera). Biološki inštitut Jovana Hadžija ZRC SAZU. Ferlin, F (ur.), 2004. Razvoj mednarodno primerljivih kazalcev biotske pestrosti v sloveniji in nastavitev monitoringa teh kazalcev - na podlagi izkušenj iz gozdnih ekosistemov. Freese, A., M. Dolek, a. Geyer & H. Stetter. 1999 (2005). Biology, distribution, and extinction of Colias myrmidone (Lepidoptera, Pieridae) in Bavaria and its situation in other European countries. Journal of Research on the Lepidoptera, 38: 51-58. Frieft, T., M. Fuchs, J. Gepp, C. Hinteregger, A. Koschuh, P. Kock & E. Zanini, 2004. Natura 2000; EU-geschutzte Pflanzen- und Tierarten in der Steiermark. Institut fur Naturschutz und Landschaftsokologie, Steiermark. Golob, A., 2004. Pregled habitatnih tipov gozdov v Sloveniji, ki v grobem ustrezajo merilom iz habitatnega priročinka EU in njihove značilnosti predlaganih območjih Natura 2000. MOPE-ARSO, Ljubljana. Jež, M. 2005. Travniški metulji in Natura 2000 v Sloveniji. Mariborski Agronom, 10(3):34-36. Johst, K., M. Drechsler, J. Thomas & J. Settele, 2006. Influence of mowing on the persistence of two endangered large blue butterfly species. Journal of Applied Ecology 43: 333-342. Jogan, N., M. Kotarac & A. Lešnik, 2004. Opredelitev območij evropsko pomembnih negozdnih habitatnih tipov s pomočjo razširjenosti značilnih rastlinskih vrst. Končno poročilo. Naročnik: MOPE, ARSO, Ljubljana. Center za kartografijo favne in flore, Miklavž na Dravskem polju. 961 str., digitalne Priloge. Jonozovič, M. 2003a. Strokovna izhodišča za vzpostavljanje omrežja Natura 2000. Rjavi medved (Ursus arctos). Naročnik: MOPE, ARSO, Ljubljana. Jonozovič, M. 2003b. Strokovna izhodišča za vzpostavljanje omrežja Natura 2000. Ris (Lynx lynx). Naročnik: MOPE, ARSO, Ljubljana. Joly, P., C. Morand & A. Cohas, 2003. Habitat fragmentation and amphibian conservation: building a tool for assessing landscape matrix connectivity. Comptes Rendus Biologies 326: 132-139. Kotarac, M., A. Šalamun & S Weldt, 2003. Strokovna izhodišča za vzpostavljanje omrežja Natura 2000: Kačji pastirji (Odonata) (končno poročilo). Naročnik: MOPE, ARSO, Ljubljana. Center za kartografijo favne in flore, Miklavž na Dravskem polju. 104 str., digitalne Priloge. Kaligarič, M. 1997. Rastlinstvo Primorskega krasa in Slovenske Istre: travniki in pašniki. Zgodovinsko društvo za južno Primorsko: Znanstveno-raziskovalno središče Republike Slovenije (Knjižnica Annales majora). Kaligarič, M., B. Trčak, B. Lipej & A Sovinc. Mapping and conservation of dry grasslands on the edge of the Mediterranean basin - difficult task after changed socio-economic trends. Paper at the 4'h European Conference on the Conservation of Wild Plants. "A workshop on implementation of the Global Strategy for Plant Conservation in Europe", Valencia (Spain), 17-20 September 2004. Kaligarič, M., A. Seliškar & P. Veen, 2003. Grasslands of Slovenia: status and conservation of semi-natural grasslands. Royal Dutch Society for Nature Conservation & Society for Natural History in Slovenia, Utrecht/Ljubljana. Koce, U. & B. Rubinič, 2005. Ogrožene vrste ptic na Krasu. Glas pliske, 2(5): 5-14. Polanšek, B., & A. Golob, 2006. Strokovne podlage načrtovanje in ohranjanje trajnostnega razvoja v območjih Natura 2000. Gozdarski inštitut Slovenije, Ljubljana. Kryštufek, B. Strokovna izhodišča za vzpostavljanje omrežij Natura 2000. Bober (Castor fiber). Končno poročilo. Naročnik: MOPE, ARSO, Ljubljana. Prirodoslovni muzej Slovenije. Ljubljana. Kryštufek, B., P. Presetnik & A. Šalamun, 2003. Strokovne osnove za vzpostavljanje omrežja Natura 2000:. Netopirji (Chiroptera) (Končno poročilo) Naročnik: MOPE, ARSO, Ljubljana. Prirodoslovni muzej Slovenije, Ljubljana. Miguel L. Munguira and José Martin. 1999 Action plan for the Maculinea Butterflies in Europe. Convention on the Conservation of European Wildlife and Natural Habitats (Bern Convention) Nature and Environment, No. 97. Poboljšaj, K. & A. Lešnik, 2003. Strokovna izhodišča za vzpostavljanje omrežja Natura 2000: Dvoživke (Amphibia) (končno poročilo). Naročnik: MOPE, ARSO, Ljubljana. Center za kartografijo favne in flore, Miklavž na Dravskem polju. 144 str., digitalne Priloge. Povz, M., D. Jesensek, P. Berrebi & A. J. Crivelli, 1996. The marble trout Salmo trutta marmoratus, Cuvier 1817 in the Soca River basin, Slovenia: an action plan. Tour du Valat, Arles. Saarinen, K., 2002. Butterfly communities in relation to changes in the management of agricultural environments. Thesis, University of Joensuu. Sket, B. 2000. Pregled in izbor jam, ki so pomembne za ohranjanje podzemske favne. Naročnik: MOPE, ARSO, Ljubljana. Slapnik, R., 2003. Strokovna izhodišča za vzpostavitev za vzpostavitev omrežja Natura 2000. Mehkužci (Mollusca), Biološki inštitut Jovana Hadžija ZRC SAZU. Tome, S. Strokovna izhodišča za vzpostavljanje omrežij Natura 2000. Močvirska sklednica (Emys orbicularis). Končno poročilo. Naročnik: MOPE, ARSO, Ljubljana. Prirodoslovni muzej Slovenije. Ljubljana. Trampuš, T., & B. Vidmar, 2004. Kanal Sv. Jerneja, kjer se med metličjem zibljejo barke. Ministrstvo za okolje, prostor in energijo, Ljubljana. Turk, R., 2004. Kartiranje habitatnih tipov na območju Strunjanskih solin in Stjuže. N-Vestnik 1(4): 3. Turk, R., 2004. Report on activities aimed at ensuring an efficient, long-term conservation of the Posidonia oceanica meadow located on the Slovenian coast between the towns of Koper and Izola in the northern Adriatic. Zavod Republike Slovenije za varstvo narave, Območna enota Piran, Piran. Warren, M., & T. Wigglesworth, no year. Marsh frittilary Euphydryas aurinia factsheet. Butterfly Conservation, Wareham. Watters, G. T., 2000. Freshwater mussels and water quality: a review of the effects of hydrologic and instream habitat alterations. Proceedings of the Freshwater Mollusc Society Symposium, 1999: 261-274. Materials from LIFE projects: Natura 2000 in Slovenia - management models and information systems http://www.zrsvn.si/life/sl/Default.asp http://www.zrsvn.si/life/sl/informacija.asp?id_meta_type=43&id_informacija=275 Establishing long-term protection of the corn crake (Crex crex) in Slovenia http://www.life-kosec.org/ http://www.life-kosec.org/index.php?idv=125 Materials from Phare programme: Cross-border cooperation between Slovenia and Austria, 2003: http://www.rec-lj.si/proj ekti/Phare_b d/Phare_bd.htm 4.2 » DETAILED PROTECTION OBJECTIVES AND MEASURES FOR THEIR ATTAINMENT ON NATURA SITES Due to its size, full Annex 4.2 is supplemented on a CD (Slovenian only). Text version is provided in pdf format (619 pages). Data are also available in two Excel tables that allow easier search and review. Ministry prepared the draft annex 4.2 on the basis of the study: Kus Veenvliet, J., 2006. Strokovne podlage za Operativni program in akcijski načrt ohranjanja biotske raznovrstnosti s programom upravljanja območij Natura 2000, s poudarkom na podrobni finančni analizi. Final report. Prepared by: Intsitute Symbiosis, Grahovo. Contracting authority: Ministry of the Environment and Spatial Planning, Ljubljana. Table »lzpisCiljev_Ukrepov_zajavnost.xls« contains all the data from the Annex 4.2, sorted by sites. A filter enables you to select the contents (site, group of sites, species, habitat type etc.) Table »lzpisCiljev_Ukrepov_Načrti.xls« is designed for planners and contains additional fields with names of plans for the use of natural resources Annex contains: s Detailed protection objectives for a habitat type or species for each individual Natura 2000 site s Measures for reaching detailed protection objectives, which are: • nature protection measures; • measures of modified use of natural resources serving to attain protection objectives; • measures of modified agricultural practice serving to attain protection objectives; • measures of water management serving to attain protection objectives; and • other measures, should they prove necessary for the creation of a favourable status of plant and animal species and habitat types. Measures for attaining each detailed protection objective are also determined, as well as legal persons responsible for the entry of a measure (detailed protection policies) into the plan for each individual area, relevant sector and adequate planning document. Ways of implementing measures from the annex: s Nature protection measures included in the work of public institutes and the Ministry of the Environment and Spatial Planning s Measures of modified use of natural resources included in sectoral plans s Measures of modified agricultural practice included in agri-environmental measures of the Rural Development Programme 2007-2013 s Water management measures later included in the water management plan and programme of measures FORESTS in a Natura area All forests are covered with forest management plans (10-year plans) and public service (the Slovenian Forest Service) takes care of their implementation. An example of measures for achieving a protection objective (Trnovski gozd) for the habitat type Illyrian Fagus sylvatica forests: A part of the internal zone of the habitat type (HT) 91K0 extends into the economic class (GR) Primorska bukovja, in which shelter-wood management is performed. The share of beech in forests should be increased, and selective thinning should be implemented to improve the plan and maintenance and accelerate transition to older development (succession) phases. HUNTING in a Natura area All hunting grounds are covered with forest management plans (10-year plans) and public service (the Slovenian Forest Service) takes care of their implementation. An example of measures for achieving a protection objective (Trnovski gozd)for the Eurasian Lynx: In the internal zone of the Eurasian Lynx, hunting is planned so that populations of larger herbivorous game are maintained at an adequate density which still allows natural the rejuvenation of forest habitat types. WATERS in a Natura area As of 2009, waters will be covered with water management programmes, detailed water management plans, a programme of measures (10-year programme), and a public service or its implementation. An example of measures for achieving a protection objective (Trnovski gozd) for the Soča Trout: Incorporating ecological requirements of the Soča Trout in water management plans primarily to preserve the volume and speed of water flow and fords. AGRICULTURAL AREAS in a Natura area Agricultural activities are steered with agri-environmental payments. An example of measures for achieving a protection objective (Trnovski gozd) for the Rock Partridge: Prevention of further overgrowing of grassland areas in the internal zone of the Rock Partridge with the reestablishment of extensive pastures. An adequate use is ensured through the agri-environmental programme, measures for preservation of extensive grasslands. By 2010 the use is maintained at 370 ha, and increased to 400 ha by 2013. FISHERIES in a Natura area All fishing waters are covered with plans on fisheries management areas and a public service (the Fisheries Research Institute of Slovenia) takes care of their implementation. An example of measures for achieving a protection objective (the Vipava Valley) for the White Bleak: Non native fish species which negatively affect the population of the White Bleak, such as the closely related Bleak,should not be introduced in the internal zone of the White Bleak. NATURE PROTECTION MEASURES in a Natura area Caves - with nature protection measures in accordance with the Nature Conservation Act and the Cave Protection Act An example of measures for achieving a protection objective (area Trnovski gozd) for Leptodirus hochenwarthii: Control over the protection of Ciganska jama in Predgriže (identification number 40493) is carried out by supervised entry. The contract on stewardship of the cave shall determine a visitor regime with spatial and time limitations that assure the protection of Leptodirus hochenwarthii. Nature protection measures — marking on the site An example of measures for achieving a protection objective (Trnovski gozd) for the Yellow Lady's Slipper: Marking of Yellow Lady's Slipper sites which inform visitors to protect the site. The Natura network is a protected area Protected area for which an adoption of a protected area management plan is envisaged. An example of measures for achieving a protection objective (Sečovlje salina) for Spartina swards: Embankments and ditches in the internal zone HT 1320 are maintained at their existing width, shape and bank structure, without planning of new excursion paths on the embankments. Subject Number Separated areas of Natura According to the Birds Directive According to the Habitats Directive Joint areas of Natura (overlapping areas are combined) Number of species according to both directives and habitat types Achieving the objectives through Protected areas management plans New protected areas Protection of caves Other nature protection measures Sectoral plans in the field of forestry Sectoral plans in the field of hunting Sectoral plans in the field of fisheries Modified agricultural practice measures Water management measures 286 26 260 231 275 9 5 113 28 156 GGE + 14 GGO 9 26 envisaged plans In 59 areas of Natura 2000 In the first phase, two water management plans 4.3 » LIST OF PLANS FOR THE USE OF NATURAL RESOURCES (I.E. PLANS WHICH MAY PROVE DIRECTLY NECESSARY FOR THE PROTECTION OF NATURA SITES) 4.3.1 » FOREST MANAGEMENT PLANS Unit name Year of ADOPTION Unit name Year of ADOPTION Adlešiči 2013 Dole 2007 Ajdovščina 2010 Dole nad Idrijo 2012 Bele Vode 2009 Dolinsko 2012 Besnica 2013 Dol-Moravče 2009 Blagovica 2008 Domžale 2007 Bled 2011 Draga 2011 Bloke 2013 Dravograd 2008 Boč 2012 Gomance 2010 Bohor 2008 Gorica 2007 Brda 2012 Goričko I 2008 Briga 2007 Goričko II 2009 Brkini II 2013 Goričko obrobje 2013 Celje 2009 Gorjanci 2008 Cerklje 2010 Gotenica 2012 Cerkno 2009 Gr intovec 2010 Čemšenik-Kolovrat 2011 Grosuplje 2012 Čičarija 2009 Hrašče-Osojnica 2007 Črmošnjice 2007 Idrija II 2008 Črna - Smrekovec 2012 Istra 2009 Črni Vrh 2010 Iška-Otave 2012 Črnomelj 2010 Javorje 2007 Destrnik 2012 Javornik 2011 Dobovec-Kum 2007 Jelendol 2010 Dobropolje 2013 Jelovica 2012 Dobrova 2007 Jesenice 2008 Unit name Year of ADOPTION Jezersko 2012 Jezerščak 2009 Jurjeva dolina 2010 Jurklošter 2007 Južno Pohorje 2010 Kamnik 2010 Kamniška Bistrica 2009 Kanomlja 2013 Kapla 2009 Kobarid 2009 Koče 2009 Kokra 2011 Kolpa 2013 Kranjska gora 2007 Kras II 2008 Lenart v Sl. Gor. 2008 Lešje 2009 Litija-Šmartno 2013 Ljubno 2007 Lobnica 2013 Logatec 2008 Logatec - Zagora 2011 Loški potok 2008 Mala gora - Ortnek 2012 Medvode 2010 Menešija 2011 Metlika 2008 Mežica 2010 Mikula-Dedna gora 2007 Mirna gora 2009 Mokrec 2012 Mokrice 2010 Most na Soči 2011 Mozelj 2009 Nanos-Hrušica 2013 Unit name Nazarje Notranji Bohinj Novo mesto - sever Novo mesto jug Obora Smuka-Stari log Okroglina Ormož Otlica Otok-Karlovica Pišece Pivka Jama - Grmada Planina Plešivec Podčetrtek Polenšak Poljane Poljanska dolina Požarje Preddvor Preserje-Rakitna Racna gora-Križna gora Radeče Radlje-levi breg Radovljica desni breg Save Radovljica levi breg Save Ravensko Ravne Ravnik Rečica Remšnik Ribnica na Pohorju Rog Rogaška Slatina Rovte 2013 2013 2009 2012 2013 2013 2007 2008 2010 2012 2012 2008 2007 2011 2007 2008 2013 2008 2012 2013 2009 2009 2013 2010 2009 2007 2009 2011 2012 2012 2011 2007 2012 2009 Unit name Ruše Selnica Senovo Sevnica Slivnica Smrečno Soča-Trenta Sodražica Solčava Sovodenj Stari trg Straža - Toplice Struge Studenec Šentjanž Šentjernej Škofja Loka Tolmin Trbovlje-Zagorje 2011 2013 2011 2013 2008 2009 2007 2008 2010 2009 2011 2008 2012 2010 2009 2010 2007 2011 2007 Unit name Trebnje II Trebnje I Trnovo Tuhinj-Motnik Velenje Velika Gora Velike Lašče Vojnik Vransko Vrbovec Vremščica Vrhe Vrhnika Vurberg-Duplek Vzhodno Pohorje Zahodno Goričko Zg. Dravsko polje Zreče Žirovnica Year of ADOPTION 2013 2011 2013 2008 2008 2007 2010 2007 2013 2011 2007 2007 2007 2010 2008 2011 2010 2011 2009 Adoption of all GGO area plans is scheduled in 2011. Name of GGE Name of GGO Name of GGE Name of GGO Bohinj Bled Gornji Grad Nazarje Mežakla Bled Luče Nazarje Pokljuka Bled Brezova reber Novo mesto Krakovo Brežice Krka Novo mesto Krško Brežice Mehovo Novo mesto Mokronog Brežice Poljane Novo mesto Marija Reka Celje Semič Novo mesto Slovenske Konice Celje Soteska Novo mesto Vitanje Celje Žužemberk Novo mesto Grčarice Kočevje Baba-Debela gora Postojna Kolpska dolina-Banja Loka Kočevje Črni dol Dletvo Postojna Postojna Ravne Kočevje Leskova dolina Postojna Stojna Kočevje Mašun Postojna Željne- Laze Kočevje Planina-Golobičevec Postojna Tržič Kranj Snežnik Postojna Zali Log Kranj Suhi vrh-Podgora Postojna Železniki Kranj Škocjan-Unec Postojna Bistra-Borovnica Ljubljana Brkini I Kraško Hrastnik Ljubljana Goriško Kraško Ivančna Gorica Ljubljana Kras I Kraško Ig Ljubljana Trnovo Kraško Kum Ljubljana Mislinja-Šentilj Slovenj Gradec Polhov Gradec Ljubljana Paški Kozjak Slovenj Gradec Polšnik Ljubljana Pohorje Slovenj Gradec Ljubljana Ljubljana Radlje-desni breg Slovenj Gradec Primskovo Ljubljana Banjščice Tolmin Lovrenc na Pohorju Maribor Baška Grapa Tolmin Osankarica Maribor Bovec Tolmin Rodni Vrh Maribor Idrija I Tolmin Slovenska Bistrica Maribor Nanos-Podkraj Tolmin Sp. Dravsko polje Maribor Predmeja Tolmin Šentilj v Sl. Goricah Maribor Vzhodne Haloze Maribor Gornja Radgona Murska Sobota Ljutomer Murska Sobota Vzhodno Goričko Murska Sobota 4.3.2 » HUNTING AREA PLANS AND WILD GAME MANAGEMENT PLANS (LUO) Name of hunting area Name wild game MANAGEMENT PLAN (LUO) Year o ADOPTK Bled Gorenjsko 2007 Bohinjska Bistrica Gorenjsko 2007 Jelovica-Ribno Gorenjsko 2007 Jezersko Gorenjsko 2007 Jošt - Kranj Gorenjsko 2007 Kranjska gora Gorenjsko 2007 Kropa Gorenjsko 2007 LPN Kozorog Kamnik Gorenjsko 2007 Nomenj-Gorjuše Gorenjsko 2007 Selca Gorenjsko 2007 Sorica Gorenjsko 2007 Fužina Gorenjsko 2007 Železniki Gorenjsko 2007 Ljubno Kamniško Savinjsko 2007 Luče Kamniško Savinjsko 2007 Mozirje Kamniško Savinjsko 2007 Rečica ob Savinji Kamniško Savinjsko 2007 Smrekovec Kamniško Savinjsko 2007 Solčava Kamniško Savinjsko 2007 Banja Loka - Kostel Kočevsko Belokranjsko 2007 Črnomelj Kočevsko Belokranjsko 2007 Dolenja vas Kočevsko Belokranjsko 2007 Draga Kočevsko Belokranjsko 2007 Dragatuš Kočevsko Belokranjsko 2007 Grosuplje Kočevsko Belokranjsko 2007 Kočevje Kočevsko Belokranjsko 2007 Lazina Kočevsko Belokranjsko 2007 Loka pri Črnomlju Kočevsko Belokranjsko 2007 Loški potok Kočevsko Belokranjsko 2007 LPN Medved Kočevsko Belokranjsko 2007 LPN Snežnik Kočevska Reka Kočevsko Belokranjsko 2007 Mala gora Kočevsko Belokranjsko 2007 Osilnica Kočevsko Belokranjsko 2007 Name of hunting area Name wild game MANAGEMENT PLAN (LUO) Year o ADOPTK Predgrad Kočevsko Belokranjsko 2007 Ribnica Kočevsko Belokranjsko 2007 Sinji vrh Kočevsko Belokranjsko 2007 Smuk-Semič Kočevsko Belokranjsko 2007 Sodražica Kočevsko Belokranjsko 2007 Struge na Dolenjskem Kočevsko Belokranjsko 2007 Suhor Kočevsko Belokranjsko 2007 Taborska jama Kočevsko Belokranjsko 2007 Vinica Kočevsko Belokranjsko 2007 Babno polje Notranjsko 2007 Begunje Notranjsko 2007 Borovnica Notranjsko 2007 Cajnarje Notranjsko 2007 Cerknica Notranjsko 2007 Gornje jezero Notranjsko 2007 Grahovo Notranjsko 2007 Ig Notranjsko 2007 Iga vas Notranjsko 2007 Javornik-Postojna Notranjsko 2007 Kozlek Notranjsko 2007 Lož - Stari trg Notranjsko 2007 LPN Ljubljanski vrh Notranjsko 2007 LPN Jelen Notranjsko 2007 Mokrc Notranjsko 2007 Nova vas Notranjsko 2007 Pivka Notranjsko 2007 Prestranek Notranjsko 2007 Rakek Notranjsko 2007 Rakitna Notranjsko 2007 Tabor Zagorje Notranjsko 2007 Tomišelj Notranjsko 2007 Trnovo Notranjsko 2007 Žilce Notranjsko 2007 Brusnice Novomeško 2007 Gorjanci Novomeško 2007 Orehovica Novomeško 2007 Name of hunting area Name wild game MANAGEMENT PLAN (LUO) Padež Novomeško 2007 Plešivica Novomeško 2007 Šentjernej Novomeško 2007 Toplice Novomeško 2007 Bistra Pohorsko 2007 Bukovje Pohorsko 2007 Fram Pohorsko 2007 Golavabuka Pohorsko 2007 Gradišče Pohorsko 2007 Hoče Pohorsko 2007 Koprivna Pohorsko 2007 LPN Pohorje Pohorsko 2007 Orlica Pohorsko 2007 Peca Pohorsko 2007 Podvelka Pohorsko 2007 Puščava Pohorsko 2007 Radvanje Pohorsko 2007 Ruše Pohorsko 2007 Šmartno na Pohorju Pohorsko 2007 Zeleni Vrh Pohorsko 2007 Kostanjevica na Krki Posavsko 2007 Podbočje Posavsko 2007 Bovec Triglavsko 2007 Čezsoča Triglavsko 2007 Drežnica Triglavsko 2007 Kobarid Triglavsko 2007 Ljubinj Triglavsko 2007 Log pod Mangrtom Triglavsko 2007 LPN Prodi - Razor Triglavsko 2007 LPN Triglav Triglavsko 2007 Podbrdo Triglavsko 2007 Smast Triglavsko 2007 Soča Triglavsko 2007 Tolmin Triglavsko 2007 Bukovje Zahodno visoko Kraško 2007 Col Zahodno visoko Kraško 2007 Name of hunting area Name wild game MANAGEMENT PLAN (LUO) Year of ADOPTION Čaven Zahodno visoko Kraško 2007 Čepovan Zahodno visoko Kraško 2007 Črna jama Zahodno visoko Kraško 2007 Dole nad Idrijo Zahodno visoko Kraško 2007 Gorica Zahodno visoko Kraško 2007 Hotedršica Zahodno visoko Kraško 2007 Hrenovice Zahodno visoko Kraško 2007 Hubelj Zahodno visoko Kraško 2007 Idrija Zahodno visoko Kraško 2007 Javornik Zahodno visoko Kraško 2007 Kozje stena Zahodno visoko Kraško 2007 Krekovše Zahodno visoko Kraško 2007 Lijak Zahodno visoko Kraško 2007 Logatec Zahodno visoko Kraško 2007 Nanos Zahodno visoko Kraško 2007 Planina Zahodno visoko Kraško 2007 Sabotin Zahodno visoko Kraško 2007 Trebuša Zahodno visoko Kraško 2007 Trnovski gozd Zahodno visoko Kraško 2007 Vipava Zahodno visoko Kraško 2007 Vojkovo Zahodno visoko Kraško 2007 Vrhnika Zahodno visoko Kraško 2007 4.3.3 » FISHERY MANAGEMENT PLANS OF A FISHERY ZONE Name of fishery zone Barjanski ribiški okoliš Bistriški ribiški okoliš Celjski ribiški okoliš Črnomaljski ribiški okoliš Črnuški ribiški okoliš Kranjski ribiški okoliš Lendavski ribiški okoliš Ljubenski ribiški okoliš Mariborski ribiški okoliš Medvoški ribiški okoliš Metliški ribiški okoliš Mirenski ribiški okoliš Mozirski ribiški okoliš Murskosoboški ribiški okoliš Novomeški ribiški okoliš O rmoški ribiški okoliš Paški ribiški okoliš Poljanski ribiški okoliš Radeški ribiški okoliš Renški ribiški okoliš Slovenjebistriški ribiški okoliš Šempetrski ribiški okoliš Škofjeloški ribiški okoliš Tržiški ribiški okoliš Vrhniški ribiški okoliš Žužemberški ribiški okoliš 4.4 » RESEARCH ACTIVITIES IN THE FIELD OF BASIC AND APPLIED SCIENCES NECESSARY FOR IMPROVING KNOWLEDGE OF THE ECOLOGY OF PLANT AND ANIMAL SPECIES AND HABITAT TYPES Set 1 Research activities for better knowledge of the ecology related to essential biotic and abiotic factors (in particular, climate factors, structures in ecosystems, flagship species in ecosystems, typical species of habitat type, competitive species, species from higher or lower trophic levels) which influence: a) the presence/absence of species b) high fluctuations in size/density of population c) reduction/expansion of range Plant and animal species or habitat types dealt with from 1a to 1c which are a higher priorities of this Strand: i. Species from the Rules on the inclusion of endangered plant and animal species in the Red List (Official Gazette of RS 103/03), classified in the categories Ex?, E, V or R, which are included in Annex 2 or 4 of the Habitats Directive, or in Annex 1 of the Bird Directive, or are endemic, with the majority of the world population/habitat area in Slovenia. ii. Other species from the Rules Determining Endangered Plant and Animal Species of the Republic of Slovenia, and habitat types endangered in Slovenia, which are included in Annex 1 of the Habitats Directive Set 2 Research activities for better knowledge of the influence of the use or management of natural resources (with different types of agriculture, forestry, fishery, water management etc.) on the factors from the first set. A higher priority of this set is research activities which deal with plant and animal species, or habitat types from Set 1. Set 3 Determining characteristics of species which may be indicators of the condition of other species from Set 1. 4.5 » MONITORING INDICATORS OF THE STATUS OF SPECIES AND HABITAT TYPES Name EU Code Monitoring MONITOl IMPLEME Active raised bogs 7110 mapping habitat types no Alpine and subalpine calcareous grasslands 6170 mapping habitat types no Siliceous alpine and boreal grasslands 6150 mapping habitat types no Alpine and Boreal heaths 4060 mapping habitat types no Alpine rivers and their ligneous vegetation with Salix elaeagnos X mapping habitat types no Alpine rivers and their ligneous vegetation with Myricaria germanica 3230 mapping habitat types no Alpine rivers and the herbaceous vegetation along their banks 3220 mapping habitat types no Limestone pavements 8240* mapping habitat types no Alkaline fens 7230 mapping habitat types no European dry heaths 4030 mapping habitat types no Mountain hay meadows 6520 mapping habitat types no Estuaries 1130 mapping habitat types no Caves not open to the public 8310 mapping habitat types no Calcareous and calcshist screes of the montane to alpine levels (Thlaspietea rotundifolii) 8120 mapping habitat types no Calcareous fens with Cladium mariscus and species of the Caricion davallianae 7210 mapping habitat types no Calcareous rocky slopes with chasmophytic vegetation 8210 mapping habitat types no Petrifying springs with tufa formation (Cratoneurion) 7220 mapping habitat types no Mudflats and sandflats not covered by seawater at low tide 1140 mapping habitat types no Natural dystrophic lakes and ponds 3160 mapping habitat types no Natural euthrophic lakes with Magnopotamion or Hydrocharition-type vegetation 3150 mapping habitat types no Hydrophilous tall herb fringe communities of plains and of the montane to alpine levels 6430 mapping habitat types no Lowland hay meadows (Alopecurus pratensis, Sanguisorba officinalis) Coastal lagoons Oligotrophic to mesotrophic standing waters with vegetation of the Littorelletea uniflorae and/or of the Isoeto-Nanojuncetea Salicornia and other annuals colonizing mud and sand EU Code Monitoring 6510 mapping habitat types 1150* mapping habitat types 3130 mapping habitat types 1310 mapping habitat types Monitoring IMPLEMENTED Posidonia beds (Posidonion oceanicae) Semi-natural dry grasslands and scrubland facies on calcareous substrates (Festuco Brometalia) (*important orchid sites) Vegetated sea cliffs of the Mediterranean coasts with endemic Limonium spp. Transition mires and quaking bogs Turloughs Rivers with muddy banks with Chenopodion rubri p.p. and Bidention p.p. vegetation Bushes with Pinus mugo and Rhododendron hirsutum (Mugo-Rhododendretum hirsuti) Spartina swards (Spartinion maritimae) Juniperus communis formations on heaths or calcareous grasslands Siliceous rocky slopes with chasmophytic vegetation Siliceous rock with pioneer vegetation of the Sedo-Scleranthion or of the Sedo albi-Veronicion dillenii Rupicolous calcareous or basophilic grasslands of the Alysso-Sedion albi Medio-European calcareous screes of hill and montane levels Mediterranean salt meadows (Juncetalia maritimi) Mediterranean and thermo-Atlantic halophilous scrubs (Sarcocornetea fruticosi) Permanent glaciers Calaminarian grasslands of the Violetalia calaminariae 1120* mapping habitat types 6210 mapping habitat types 1240 mapping habitat types 7140 mapping habitat types 3180* mapping habitat types 3270 mapping habitat types 4070 mapping habitat types 1320 mapping habitat types 5130 mapping habitat types 8220 mapping habitat types 8230 mapping habitat types 6110 mapping habitat types 8160 mapping habitat types 1410 mapping habitat types 1420 mapping habitat types 8340 mapping habitat types 6130 mapping habitat types no no no EU Code Monitoring Monitoring IMPLEMENTED Molinia meadows on calcareous, peaty or clayey-silt-laden soils (Molinion caeruleae) Hard oligo-mesotrophic waters with benthic vegetation of Chara spp. Depressions on peat substrates of the Rhynchosporion Water courses of plain to montane levels with the Ranunculion fluitantis and Callitricho-Batrachion vegetation Species-rich Nardus grasslands, on siliceous substrates in mountain areas (and submountain areas in Continental Europe) Eastern sub-Mediterranean dry grasslands (Scorzoneratalia villosae) Western Mediterranean and thermophilous scree (Note: included in 8160*) Annual vegetation of drift lines Bog woodland Luzulo-Fagetum beech forests Illyrian Fagus sylvatica forests (Aremonio-Fagion) Illyrian oak-hornbeam forests (Erythronio-carpinion) Tilio-Acerion forests of slopes, screes and ravines 6410 mapping habitat types 3140 mapping habitat types 7150 mapping habitat types 3260 mapping habitat types 6230* mapping habitat types 62A0 mapping habitat types 8130 mapping habitat types 1210 mapping habitat types 91D0 forest monitoring 9110 forest monitoring 91K0 forest monitoring 91L0 forest monitoring 9180 forest monitoring no yes yes yes yes yes Acidophilous Picea forests of the montane to alpine levels (Vaccinio-Piceetea) 9410 forest monitoring yes Alluvial forests with Alnus glutinosa and Fraxinus excelsior (Alno-Padion, Alnion incanae, Salicion albae) 91E0 forest monitoring yes Riparian mixed forests of Quercus robur, Ulmus laevis and Ulmus minor, Fraxinus excelsior or Fraxinus angustifolia, along the great rivers - Note: included in 91E0* forest monitoring yes Name EU Code Status of MONITORING IN 2006 Monitoring type Rosalia alpina 1087 planned (development of method) targeted monitoring Colias myrmidone 4030 to be established targeted monitoring Coenonympha oedippus 1071 to be established targeted monitoring Ciconia ciconia A031 implemented targeted monitoring Lagopus mutus helveticus A408 implemented targeted monitoring Charadrius alexandrinus A138 implemented targeted monitoring Gyps fulvus A078 implemented targeted monitoring Haliaeetus albicilla A075 implemented targeted monitoring Ficedula albicollis A321 implemented targeted monitoring Castor fiber 1337 to be established targeted monitoring Morimus funereus 1089 planned (development of method) targeted monitoring Ixobrychus minutus A022 to be established targeted monitoring Proteus anguinus 1186 to be established targeted monitoring Lanius minor A339 implemented targeted monitoring Larus melanocephalus A176 implemented targeted monitoring Miniopterus schreibersii 1310 implemented targeted monitoring Myotis capaccinii 1316 implemented targeted monitoring Leucorrhinia pectoralis 1042 to be established targeted monitoring Anisus vorticulus 4056 to be established targeted monitoring Leptodirus hochenwarti 4019 planned targeted monitoring Osmoderma eremita 1084 planned (development of method) targeted monitoring Porzana porzana A119 implemented targeted monitoring Cerambyx cerdo 1088 planned (development of method) targeted monitoring Lullula arborea A246 implemented targeted monitoring Rhysodes sulcatus 4026 planned (development of method) targeted monitoring Falco naumanni A095 to be established targeted monitoring Rhinolophus euryale 1305 implemented targeted monitoring Ophiogomphus cecilia 1037 to be established targeted monitoring Crex crex A122 implemented targeted monitoring Coenagrion ornatum 4045 to be established targeted monitoring Alectoris graeca saxatilis A412 implemented targeted monitoring Strix uralensis A220 implemented targeted monitoring Name eu Code Status of monitoring in 2006 Monitoring type Gallinago gallinago A153 to be established targeted moni toring Rana latastei 1215 implemented targeted moni toring Sterna albifrons A195 implemented targeted moni toring Porzana parva A120 implemented targeted moni toring Aquila pomarina A089 implemented targeted moni toring Rhinolophus hipposideros 1303 implemented targeted moni toring Emys orbicularis 1220 to be established targeted moni toring Lycaena dispar 1060 to be established targeted moni toring Carabus variolosus 4014 planned targeted moni toring Sterna hirundo A193 implemented targeted moni toring Austropotamobius torrentium 1093 planned targeted moni toring Myotis myotis 1324 implemented targeted moni toring Lynx lynx 1361 implemented targeted moni toring Bombina bombina 1188 to be established targeted moni toring Myotis blythii 1307 implemented targeted moni toring Vertigo angustior 1014 to be established targeted moni toring Sylvia nisoria A307 implemented targeted moni toring Caprimulgus europaeus A224 implemented targeted moni toring Himantopus himantopus A131 implemented targeted moni toring Austropotamobius pallipes 1092 planned targeted moni toring Ursus arctos 1354 implemented targeted moni toring Lucanus cervus 1083 planned targeted moni toring Falco peregrinus A103 implemented targeted moni toring Dendrocopos medius A238 implemented targeted moni toring Maculinea teleius 1059 to be established targeted moni toring Barbastella barbastellus 1308 implemented targeted moni toring Maculinea nausithous 1061 to be established targeted moni toring Euphydryas (Eurodryas) aurinia 1065 to be established targeted moni toring Myotis emarginatus 1321 implemented targeted moni toring Bubo bubo A215 implemented targeted moni toring Myotis bechsteini 1323 implemented targeted moni toring Rhinolophus ferrumequinum 1304 implemented targeted moni toring Otus scops A214 Lutra lutra 1355 Alcedo atthis A229 Canis lupus 1352 Emberiza hortulana A379 Coracias garrulus A231 Aythya fuligula A061 Podiceps nigricollis A008 Phalacrocorax carbo sinensis A391 Fulica atra A125 Egretta garzetta A026 Tachybaptus ruficollis A004 Mergus albellus A068 Anas platyrhynchos A053 Rallus aquaticus A118 Anser fabalis A039 Gavia arctica A002 Larus ridibundus A179 Aythya ferina A059 Calidris alpina A149 Egretta alba A027 Mergus merganser A070 Bucephala clangula A067 Anas penelope A050 implemented to be established implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented implemented targeted monitoring targeted monitoring targeted monitoring targeted monitoring targeted monitoring targeted monitoring international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) international waterbird census (IWC) Name eu Code Status of monitoring in 2006 Monitoring typ Phoenicurus phoenicurus A274 planned farmland bird index monitoring Coturnix coturnix A113 planned farmland bird index monitoring Vanellus vanellus A142 planned farmland bird index monitoring Saxicola rubetra A275 planned farmland bird index monitoring Sylvia communis A309 planned farmland bird index monitoring Lanius collurio A338 planned farmland bird index monitoring Upupaepops A232 planned farmland bird index monitoring Jynx torquilla A233 planned farmland bird index monitoring Gobio albipinnatus 1124 to be established monitoring of waters Leuciscus souffia 1131 to be established monitoring of waters Aspius aspius 1130 to be established monitoring of waters Misgurnus fossilis 1145 to be established monitoring of waters Barbus plebejus 1137 to be established monitoring of waters Gymnocephalus baloni 2555 to be established monitoring of waters Cottus gobio 1163 to be established monitoring of waters Gobio kessleri 2511 to be established monitoring of waters Lethenteron zanandreai 1197 to be established monitoring of waters Rutilus rubilio 1136 to be established monitoring of waters Barbus caninus 1138 to be established monitoring of waters Unio crassus 1032 to be established monitoring of waters Cobitis taenia 1149 to be established monitoring of waters Chalcalburnus chalcoides 1141 to be established monitoring of waters Rhodeus sericeus amarus 1134 to be established monitoring of waters Rutilus pigus 1114 to be established monitoring of waters Barbus meridionalis 1138 to be established monitoring of waters Eudontomyzon spp. 1098 to be established monitoring of waters Alburnus albidus 1120 to be established monitoring of waters Chondrostoma genei 1115 to be established monitoring of waters Pelecus cultratus 2522 to be established monitoring of waters Status of Name eu Code í monitoring in 2006 Monitoring type Gymnocephalus schraetzer 1157 to be established monitoring of waters Aphanius fasciatus 1152 to be established monitoring of waters Salmo marmoratus 1107 to be established monitoring of waters Hucho hucho 1105 to be established monitoring of waters Zingel streber 1160 to be established monitoring of waters Cobitis elongata 2533 to be established monitoring of waters Umbra krameri 2011 to be established monitoring of waters Sabanejewia aurata 1146 to be established monitoring of waters Gobio uranoscopus 1122 to be established monitoring of waters Vertigo geyeri 1013 to be established checking of species presence Congeria kusceri 4065 to be established checking of species presence Bombina variegata 1193 to be established general monitoring Picus canus A234 to be established general monitoring Triturus carnifex 1166 to be established general monitoring Elaphe quatuorlineata 1279 to be established checking of species presence Cucujus cinnaberinus 1086 planned checking of species presence, then decission on monitoring type Graphoderus bilineatus 1082 planned checking of species presence, then decission on monitoring type Stephanopachys substriatus 1927 planned checking of species presence, then decission on monitoring type Buxbaumia viridis 1386 to be established checking of species presence, then decission on monitoring type Dicranum viride 1381 to be established checking of species presence, then decission on monitoring type Drepanocladus vernicosus 1393 to be established checking of species presence, then decission on monitoring type Mannia triandra 1379 to be established checking of species presence, then decission on monitoring type Cordulegaster heros 4046 to be established checking of species presence, then decission on monitoring type 4.6 » LIST OF INVESTMENTS FOR THE IMPLEMENTATION OF SPECIFIC MEASURES FOR THE MANAGEMENT OF NATURA AREAS AND PROTECTED AREAS AND DEVELOPMENT ON THE BASIS OF OPPORTUNITIES THEY PRESENT Set A — National programmes of investments and services related to the development of park infrastructure for the development of tourist offers in protected areas An agreement between the Ministry of the Economy and the Ministry of the Environment and Spatial Planning on the possibilities of co-funding within the Operational Programme for Strengthening Regional Development Potentials, development priority 3.5.3. - Integration of Natural and Cultural Potentials, priority orientation 3.5.3.1. Increasing Competitiveness for Tourist Economy will be concluded for a part of the investments from the list below. Group Infrastructure for public use (cycle paths, car parks, SANITATION FACILITIES, CURBING TRAFFIC) no. List of investments and services Park 1. Central reception centre for visitors to Ljubljansko barje Regional Park (information centre with ticket sales, literature, memorabilia, domestic craft products, agricultural products; guide service, exhibition area, presentation area, management of the park for nongovernmental organisations). Ljubljansko barje Landscape Park 2. Thematic educational paths (for the whole area of the Ljubljansko barje Regional Park - nature, natural values, ecosystem, geology, geography, history, cultural heritage, ethnology, archaeology), with the construction of the related infrastructure (observation posts, lookouts, boardwalks, marking system), supporting infrastructure (info-points, parking lots, communal infrastructure, sanitation facilities), presentation and promotion. Ljubljansko barje Landscape Park Group 2: Infrastructure for visiting protected areas (information centres, OBSERVATION POSTS, LOOKOUTS, MARKING, FOOTPATHS, NATURAL SCIENCE AND CULTURAL PATHS, EDUCATIONAL PATHS) no. List of investments and services Park 3. Reconstruction of Grad Castle (finalisation of the castle building, arrangement of infrastructure and park surroundings, centre for the interpretation of nature, and tasting rooms for local products). Goričko Landscape Park 4. Three information centres in the park (on the Savinja, Kamnik and Gorenjska side). Kamnik-Savinja Alps Regional Park 5. Reconstruction works on Kozjanka Castle - info-centre. Kozjansko Regional Park 6. Construction of an information centre and park infrastructure in the landscape park. Kolpa Landscape Park 7. Information-tourist centre Cerkniško jezero (15 x 8m) and an outdoor information system of tourist promotion boards and other offers from this programmes, with an information point. Notranjska Regional Park 8. Establishment of park, construction of two information centres and arrangement of park infrastructure in Pohorje. Pohorje Regional Park 9. Establishment of park, construction of two information centres and arrangement of park infrastructure in Notranjska. Snežnik Regional Park 10. Sanitation of the access road to Lera in three functional units: on the right bank (view from the civic building) arrange footpath, which will be separated from the transport path for vehicles; the central road needs to be reinforced and covered with asphalt layer and the left bank has to be reinforced). Sečovlje Salina Nature Park 11. Construction of access path (1,100 m long wooden passage) for visitors to the Sečovlje Salina Nature Park. Sečovlje Salina Nature Park 12. Planning zones around Rudnik and a new entrance to the park (car parks, catering and sales facilities). Besides the arrangement of access for visitors, freshwater wetlands as secondary habitats for endangered species (parking lots, catering and sales facilities) have to be arranged. Sečovlje Salina Nature Park 13. Construction of the information centre and park infrastructure in the Strunjan Landscape Park. Strunjan Landscape Park 14. Reconstruction and establishment of infrastructure in the following caves: Mahorčičeva jama, Mariničeva jama, Šumeča jama and Mala dolina; reconstruction of paths, two bridges, fences and walls, and of damaged paths and electrification in closed parts of the caves, and the installation of video surveillance of tourist paths in the caves. Škocjan Caves Regional Park 15. Construction of a multimedia hall. Škocjan Caves Regional Park 16. Reconstruction of the house at Matavun 8. Škocjan Caves Regional Park 17. Information centre of Triglav National Park in Bled, phase II. Triglav National Park no. List of investments and services Park 18. Information points and stations of Triglav National Park Bled, phase III. Triglav National Park 19. Information centre of Triglav National Park in Trenta. Triglav National Park 20. Information centre in Triglav National Park - information points and stations in Triglav National Park (in Kobarid, Mojstrana and Bohinj). Triglav National Park 21. Construction of an information centre with manoeuvring areas, two observation posts, a stable with a paddock and access object (GOI part), maintenance of the landscape around objects. Škocjanski zatok Nature Reser ve Group 3: Development of new tourist products no. List of investments and services Park 22. Tourist development of the Podvolovljek area for natural science tourism. Kamnik-Savinja Alps Regional Park 23. Traditional house. Kamnik-Savinja Alps Regional Park Set B — A set of project proposals for co-funding in the areas of Natura 2000 which are protected or planned to be protected Group Infrastructure for public use (cycle paths, parking lots, sanitary FITTINGS, CURBING TRAFFIC) List of investments and services Park Funding source development priorities sub-programmes Creating crossing places for animals at black spots where roads are not planned to be renovated. Goričko Landscape Park ERDF 3.5.4.1 Regional development programmes 2 b.) Development projects in areas with special protection arrangements and in tourist areas Finalisation of the arrangement of cycle paths and footpaths. Goričko Landscape Park ERDF 3.5.4.1 Regional development programmes 2 b.) Development projects in areas with special protection arrangements and in tourist areas Information infrastructure (Luče). Kamnik- Savinja Alps Regional Park ERDF 3.5.4.1 Regional development programmes 2 b.) Development projects in areas with special protection arrangements and in tourist areas Construction of parking lots for Velika Planina. Kamnik- Savinja Alps Regional Park ERDF 3.5.4.1 Regional development programmes 2 b.) Development projects in areas with special protection arrangements and in tourist areas Cycle path network. Kozjansko Regional Park ERDF 3.5.4.1 Regional development programmes 2 b.) Development projects in areas with special protection arrangements and in tourist areas Construction of a network (road metal, uniform marking, rest spots and observation spots) of circular cycle routes (cycle rental service and repair services along a path connected to farms); paths for trekking, riding, horse carriages and cross-country skiing (various entry points). Ljubljansko barje Landsape Park ERDF 3.5.4.1 Regional development programmes 2 b.) Development projects in areas with special protection arrangements and in tourist areas List of investments and services Park Funding source development priorities sub-programmes Construction of 210 kilometres of cycle-recreation-information paths (construction and setting up of information boards, rest spots and adequate roadside signposts). Notranjska Regional Park ERDF 3.5.4.1 Regional development programmes 2 b.) Development projects in areas with special protection arrangements and in tourist areas Museum of Slovenian and World S peleolog y. Notranjska Regional Park ERDF 3.5.3 Integration of natural and cultural potential 3.5.3.2 Networking of cultural potential Educational-information footpath in Rakov Škocjan. Notranjska Regional Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas Mobile ornithology station (for further research and monitoring of bird population and their migration routes). Notranjska Regional Park LIFE + Rehabilitation of sea and river high-water level embankments in Sečovlje Salina Nature Park provide flood protection for salt fields and cultural heritage objects, and conditions for the preservation of species and habitats and security for a wider area of Portorož Airport and surrounding settlements; the majority of embankments need rehabilitation. Sečovlje Salina Nature Park ERDF 3.5.3 Integration of natural and cultural potential 3.5.3.2 Networking of cultural potential The sewage system in Sečovlje Salina Nature Park, with the construction of the 3rd phase of the system, which will cover the remaining areas of the saltpans (the manager has already set up the basic sewage network in the area of Lera and connected it to the central collector in the foothills of Seča). Sečovlje Salina Nature Park ERDF 3.5.4.1 Regional development programmes 2 b.) Environment infrastructure Construction of a sewage system and waste water drainage from a narrower area of Škocjan Caves Regional Park. Škocjan Caves Regional Park ERDF 3.5.4.1 Regional development programmes 2 b.) Environment infrastructure Construction of an anti-noise barrier at the connection to the Bertoška slip road. Škocjanski zatok Nature Reserve ERDF List of investments and services Park Funding source development priorities sub-programmes Renaturation of Jezerce, with the project documentation. Škocjanski zatok Nature Reserve ERDF Establishment of a water pumping station. Škocjanski zatok Nature Reserve ERDF Purchase of a basic herd and agricultural mechanisation. Škocjanski zatok Nature Reserve ERDF Group 2: Infrastructure for visiting protected areas (information centres, OBSERVATION POSTS, LOOKOUTS, MARKING, FOOTPATHS, NATURAL SCIENCE AND CULTURAL PATHS, EDUCATIONAL PATHS) List of investments and services Park Funding source development priorities sub-programmes Arrangement of information points for the promotion of a comprehensive tourist offer at the entry points of the park. Kamnik-Savinja Alps Regional Park ERDF 3.5.4.1 Regional development programmes 2 b.) Development projects in areas with special protection arrangements and in tourist areas Arrangement of cycle paths. Kamnik-Savinja Alps Regional Park ERDF 3.5.4.1 Regional development programmes 2 b.) Development projects in areas with special protection arrangements and in tourist areas Curbing of mo tor traffic (arrangement of car parks at entry points and traffic arrangements in the park). Kamnik-Savinja Alps Regional Park ERDF 3.5.4.1 Regional development programmes 2 b.) Development projects in areas with special protection arrangements and in tourist areas Along the botanical path of Baron Žiga Zois. Kamnik-Savinja Alps Regional Park ERDF 3.5.4.1 Regional development programmes 2 b.) Development projects in areas with special protection arrangements and in tourist areas Integral arrangement of an eco-village in Trebeže. Kozjansko Regional Park ERDF 3.5.3 Integration of natural and cultural potential 3.5.3.2 Networking of cultural potential List of investments and services Park Funding source development priorities sub-programmes Reconstruction of mills (Levstik's Mill, with a dam on the Bistrica River, Kukovičič's Mill and Preskar's Mill). Kozjansko Regional Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas Arrangement of Pišece Castle (interior and exterior public utility works). Kozjansko Regional Park ERDF 3.5.4.1 Regional development programmes 2.b.) Environment infrastructure Establishment of a tourist-information centre at Podsreda 40. Kozjansko Regional Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas Establishment of a tourist-information centre in Pišece. Kozjansko Regional Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas System of uniform marking - information and direction boards (natural and cultural heritage, paths, tourist offer, farms, promotion material ...). Ljubljansko barje Landsape Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas Setting up of entry points to the park. Ljubljansko barje Landsape Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas Entry-information point at Cerkniško Lake - construction of a car park for 85 cars and 5 buses and all requisite infrastructures. Notranjska Regional Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas Transformation of the Drnici House into an information point and observation post for visitors to Sečovlje Salina Nature Park. Sečovlje Salina Nature Park ERDF 3.5.3 Integration of natural and cultural potential 3.5.3.2 Networking of cultural potential Processing of beekeeping products. Škocjan Caves Regional Park ERDF Setting up of an information network in the influence area of Škocjan Caves Regional Park and in a wider area around the park (Dane). Škocjan Caves Regional Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas List of investments and services Park Funding source development priorities sub-programmes 1 Arrangement of mountain pastures (barns, cheese dairies and lodgings considering the energy needs of mountains, water supply and processing of technological and sewage waters; arranging access to pastures, car parks and traffic arrangements). Triglav National Park RDP Construction of cycle, bridle, trekking, and educational paths. Triglav National Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas Interior decoration of objects, presentation and exhibitions. Škocjanski zatok Nature Reserve ERDF Group 3: New entrepreneurial opportunities - management, support for telework, SUPPORT FOR COMPANIES AND E-COMPANIES DEALING WITH SUSTAINABLE DEVELOPMENT List of investments and services Park Funding source development priorities sub-programmes Educating members of agricultural collectives to undertake natural science tourism. Kamnik-Savinja Alps Regional Park RDP Construction of a composting plant. Kozjansko Regional Park ERDF 3.5.4.1 Regional development programmes 2.b.) Environment infrastructure Guide service (trained, licensed guides regular, organised and specialised guidance). Ljubljansko barje Landscape Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas Processing of agricultural products (meat, vegetables) and direct sales. Ljubljansko barje Landscape Park RDP Development of spa tourism on the basis of petola and secondary salt harvesting products - sustainable tourism (possibilities for the development of 'outdoor thalassotherapy', including research, primarily on petola) and outlines for practical approaches to the organisation of the area). Sečovlje Salina Nature Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas Group 4: Increasing the income of local inhabitants - supplementary ACTIVITIES ON FARMS, TRADITIONAL AND COMPLEMENTARY MEDICINE, SOUVENIRS, DIRECT SALES, DOMESTIC ARTS AND CRAFTS, SOCIAL FARMS List of investments and services Park Funding source development priorities sub-programmes Construction of drying rooms and cooling rooms for fruit. Kozjansko Regional Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas Beekeeping (production of honey and other beekeeping products). Ljubljansko barje Landscape Park RDP Herbalism (traditional and complementary medicine). Ljubljansko barje Landscape Park RDP Horse breeding (sport horses, domestic breeds - riding, horse carriage riding). Ljubljansko barje Landscape Park RDP Group 5: Development of new tourist products Seznam investicij in storitev Park Finančni vir razvojne prioritete Podprogrami Revitalisation, use and management of lake waters, (Krašči, Ropoča, Bukovnica, Hodoš); arrangement of water courses and river banks (Ledave, Krke, Kučnice). Goričko Landscape Park ERDF 3.5.4.1 Regional development programmes 2.b.) Development projects in areas with special protection arrangements and in tourist areas Eco-trademark: all products and services originating from the regional park - agriculture, tourism, sport and recreation. Kolpa Landscape Park RDP Tourism on farms - open door farms and ecological tourist farms (sale of agricultural products, traditional culinary art, picnic areas (maintenance, renting), accommodation capacities, camping possibilities. Events (agricultural fairs, sale of products, presentation of nature-friendly activities, folklore shows). Ljubljansko barje Landscape Park RDP Eco-trademark - all products and services originating from the Ljubljansko barje Landsape Park: agriculture, tourism, sport and recreation. Ljubljansko barje Landscape Park RDP Orchard with old tree varieties, old fruit drying room and educational path. Notranjska Regional Park RDP Creating the Triglav National Park trademark. Triglav National Park RDP Development and marketing of the reconstructed nature reserve at Škocjanski zatok as a new eco-tourist destination. Škocjanski zatok Nature Reserve ERDF Set C — A set of project proposals (types of investment and services) for priority funding in Natura areas, which can help preserve Natura areas and increase their potential for tourist development and the development of regions A.) More detailed planning of the implementation of measures from Annex 4.2 of the Operative programme - 2000 programme for Natura areas, or more detailed planning of tourist infrastructure B.) Implementation of measures from Annex 4.2 of the Operative Programme -programme of the areas in Natura 2000 C.) Establishment and maintenance of infrastructure for directing visits in Natura areas or in their narrower protected areas (information centres, observation posts, lookouts, markings, footpaths, natural science and cultural paths, educational paths) D.) Establishment and maintenance of public infrastructure (bicycle paths, parking lots, sanitary fittings, curbing traffic) for directing visit in the areas of Natura or their narrower protected areas E.) Stimulation of development of countryside and natural science tourism with respect to the protection of Natura areas s providing new accommodation capacities s establishing a network of local guides s support for marketing local products s support for the development of new tourist products (primarily from ecological tourist farm, 'working' farms, tourist product for disabled people, photo hunting, eco-culinary art, bicycle and trekking tourism) 4.7 » TARGET RESEARCH OR STUDIES FOR SETTING UP OBJECTIVES AND MEASURES Area name Ajdovska planota Kras Kočevsko Species name / ht Greater Mouse-Eared Bat Greater Mouse-Eared Bat Vejar Mirna Olm Coenagrion ornatum Coenagrion ornatum Kočevsko Leptodirus hochenwarthii Kras Euplagia quadripunctaria Kamnik-Savinja Alps Euplagia quadripunctaria Pohorje Pregara - travišča Pohorje Ložnica Ložnica Gradac Sava - Medvode -Ježica (in the decree: Sava - Medvode - Kresnice) Kras Euplagia quadripunctaria False Ringlet Marsh Fritillary Dusky Large Blue Scarce Large Blue Congeria kusceri Vertigo angustior Vertigo angustior Study content In the Church of St. Mary of the Assumption in Dolnja Straža research is carried out in order to determine to which species the colony of bats belongs and to propose adequate protective measures. Research is carried out in the cave Jama v doktorjevi ogradi in order to determine to which species the colony of bats belongs and to propose adequate protective measures. Inspect the status of the preservation of species. Ecological research is carried out in the area of the internal zone of Coenagrion ornatum aimed at providing data for concrete measures for the protection of the species. An ecological research is carried out in the area of the internal zone of Coenagrion ornatum, aimed at providing data foe concrete measures for the protection of the species. Inspect the status of preservation of species. Inspect the status of preservation of species. Inspect the status of preservation of species. Inspect the status of preservation of species. Inspect the status of preservation of species. Inspect the status of preservation of species. Inspect the status of preservation of species. Inspect the status of preservation of species. Research is carried out in pSCI Gradac to establish the status of the Congeria kusceri population, and necessary protective measures are proposed. An analysis of sediment at the source of the Krupa River (search for potential dead specimens) is necessary. Inspect the status of preservation of species. Inspect the status of preservation of species. Area name Škocjanski zatok Savinja pri Šentjanžu (associated in the Savinja area) Species name / ht Vertigo angustior Alpine rivers and ligneous vegetation with grey willow (Salix eleagnos) along their banks Study content Inspect the status of preservation of species. Inspect the status of preservation of habitat type. Temenica Kočevsko Kras Kamnik-Savinja Alps Peca Raduha Bohor Porezen Porezen Kočevsko Water courses of plain to montane levels with the Ranunculion fluitantis and Callitricho-Batrachion water vegetation Water courses of plain to montane levels with Ranunculion fluitantis and Callitricho-Batrachion water vegetation Rupicolous calcareous or basophilic grasslands of the Alysso-Sedion albi Alpine and subalpine calcareous grasslands Alpine and subalpine calcareous grasslands Alpine and subalpine calcareous grasslands Semi-natural dry grasslands and scrubland facies on calcareous substrates (Festuco Brometalia) (* important orchid sites) Hydrophilous tall herb fringe communities of plains, and of the montane to alpine levels Vrhe - povirno barje Alcaline fens Calcareous rocky slopes with chasmophytic vegetation Caves closed to the public Inspect the status of preservation of habitat type. Inspect the status of preservation of habitat type. Inspect the status of preservation of habitat type. Research should be carried out in the internal zone HT 6170 to determine an adequate arrangement of extensive pasture. Research should be carried out in the internal zone HT 6170 to determine an adequate arrangement of extensive pasture. Research should be carried out in the internal zone HT 6170 to determine an adequate arrangement of extensive pasture. Inspect the status of preservation of habitat type. Inspect the status of preservation of habitat type. Inspect the status of preservation of habitat type. Inspect the status of preservation of habitat type. Inspect the status of preservation of habitat type. Procedure of the preparation of the Natura 2000 site management Programme November 2006 Preparation of key content of the Programme in cooperation with public services (from the fields of nature conservation, forestry, hunting, fishery, water management and agriculture) and drafters of programmes for drawing EU funds Presentation of the first draft of the Programme to the expert public (universities, institutes, expert societies), the Nature Conservation Institute, and managers of protected areas, and modifications of objectives and measures Presentation of the amended draft of the Operational Programme to key participants (the Chamber of Agriculture and Forestry - the Agriculture Advisory Service, the Slovenian Forest Service) and harmonisation of measures in respect to their feasibility The second draft of the Programme November 2006 - March 2007 Additional harmonisation with the Institute of the Republic of Slovenia for Nature protection April-June 2007 Public presentation of the draft Pro gramme (website of the Ministry for the Environment and Spatial Planning and two workshops) and harmonisation with local authorities, NGOs, key participants and public services June-August 2007 Coordination of feedback from the public presentation with sectors and inter-sector coordination September 2007 Consent from all ministries and services, presentation before the Government Committee on the Economy September 2007 Approved by the Council for Sustainable Development October 2007 Adopted by the Government of the Republic of Slovenia Text: Andrej Bibič, Breda Ogorelec (pp. 14-15) Edited by: Breda Ogorelec Translated by: Blaž Trebar (Amidas d.o.o.), Zlatko Midžić (4.4, 4.6, 4.7), PSD d.o.o. (pp. 5-9) Production: Cover page photo: Iztok Škornik Photographs: Matjaž Bedjanič, Luka Božič, Andraž Čarni, Hjalma Dahm, Darja Erjavec, Andrej Gogala, Elizabeta Habič, Andrej Hudoklin, Mira Ivanovič, Nejc Jogan, Mitja Kaligarič, Simona Kaligarič, Bojan Marčeta, Andrej Martinčič, Tomaž Mihelič, Ciril Mlinar, Hrvoje Oršanič, Mirko Perušek, Katja Poboljšaj, Slavko Polak, Primož Presetnik, Peter Skoberne, Božidar Šere, Borut Štumberger, Roman Šimic, Iztok Škornik, Sonja Škornik, Branka Trčak, Iztok Tomažič, Martin Vernik, Milan Vogrin Drawings: Marjan Vaupotič, Jurij Mikuletič (p. 68) DEsiGN: Ivana Kadivec PRiNT: Bograf Ministrstvo za okolje in prostor, 2007 Republic of Slovenia - Ministry of the Environment and Spatial Planning TÎr & NATURA 201 ISBN 978-961-6392-58-7 9789616392587